Government Proposal · Draft

One Big Change Kenya

National Founding Implementation Programme: a budgeted proposal and implementation plan for Ministry, procurement, legal and financial scrutiny. KSh 84.37 million commission, September-December 2026, ten schools across ten counties.

Executive Summary

Kenya has already set the national education direction through Competency-Based Education (CBE), Curriculum (CBC) and Assessment (CBA). The next challenge is not designing policy. It is helping schools with different strengths, circumstances and resources turn that direction into consistent, sustainable practice.

This proposal seeks a KSh 84.37 million founding implementation commission to prove whether the One Big Change model can strengthen practical delivery across 10 materially different Kenyan contexts in 10 different counties.

The 90-day programme runs from 15 September to 15 December 2026. It is deliberately limited in scale. Its purpose is to generate the evidence, delivery architecture and costed plan required for a national Year 1 decision (50 LocaeHubs / 500 Core Schools / 6,000 Connected Schools).

Core purpose

To prove whether the One Big Change implementation model works across different Kenyan contexts, and whether it produces sufficiently robust evidence to justify a national scale decision - before Government is asked to commission national scale.

Programme objectives

Understand barriers

Identify what prevents consistent CBE/CBC/CBA implementation across different school contexts.

Distinguish context

Separate common nationwide barriers from those specific to geography or infrastructure.

Test support mechanisms

Determine which combinations of coaching, development, peer learning and resources change practice.

Build sustainability

Embed capability within schools and future LocaeHubs rather than permanent external intervention.

Design national scale

Define the governance, staffing, funding and infrastructure to move from 10 to 6,000 connected schools.

Produce a costed plan

Deliver an evidenced, costed Year 1 architecture for Government decision at the December Decision Gate.

KSh 84.37M

Total proposed commission

10 schools

Across 10 counties

90 days

15 Sep - 15 Dec 2026

1. Purpose of the Proposal

The purpose of this proposal is to secure Government approval to commission a national founding implementation programme.

The founding phase is not a commitment to deliver intensive implementation to 6,000 schools during the first 90 days. Its purpose is to answer a single, vital question before any national scale is considered:

“Does the One Big Change implementation model work across different Kenyan contexts, and does it produce sufficiently robust evidence to justify a national scale decision?”
2. National Context and Implementation Need

Kenya has made significant progress in developing Competency-Based Education. However, the challenge of implementation remains. Schools face different combinations of:

  • Teacher capability and confidence
  • Leadership readiness
  • Facilities and specialist equipment
  • Technology and connectivity
  • Learner wellbeing and inclusion
  • Assessment practice
  • Family and community understanding

This proposal directly addresses the implementation gap.

Joyful young Kenyan pupil in class, representing the learners at the centre of the programme

The founding programme exists to serve learners across materially different Kenyan contexts.

3. The Government Opportunity

Policy alignment

Directly supports KNEC's 2026 rollout of Competency-Based Assessment (CBA) in Senior Schools.

Political neutrality

The programme is positioned as infrastructure for implementation. It survives changes in administration.

Public procurement compliance

Designed to meet PPRA standards: fair, equitable, transparent, competitive and cost-effective.

Traction partner leverage

Government funding can unlock KSh 1 billion to KSh 3 billion in additional partner resources and equipment.
4. One Big Change Kenya: Proposed Intervention

What we are proposing to deliver by 15 December 2026:

  • Fully operational Kenyan entity and governance structure.
  • Kenyan Advisory Committee in place.
  • 10 founding schools selected and onboarded across 10 different counties.
  • 10 complete Change Lens baselines and school implementation plans.
  • 20 MicroSummit moments delivered (diagnostic and learning).
  • National implementation picture (common barriers vs contextual differences).
  • Approximately KSh 1.75 billion costed Year 1 national architecture and plan.
5. Programme Objectives

1. Understanding barriers

What prevents consistent CBE/CBC/CBA implementation across different school contexts?

2. Identifying contextual differences

Which barriers are common nationwide, and which are specific to geography or infrastructure?

3. Testing support mechanisms

What combinations of coaching, teacher development, peer-learning and resources actually change practice?

4. Building sustainability

Which capabilities can be embedded within schools and future LocaeHubs rather than requiring permanent external intervention?

5. Designing national scale

What governance, staffing, funding and infrastructure are required to move from 10 schools to 6,000 connected schools?
6. 90-Day National Founding Programme

Weeks 1-2 (15-30 Sep): Mobilise and Confirm

Confirm governance and ten schools. Appoint champions and evidence contacts. Train champions, configure Change Lens tools and establish data and safeguarding controls.

Milestone: M1 - 10 schools ready for baseline

Weeks 3-6 (Oct): Diagnose & Prioritise

In-person fieldwork in all ten counties. Complete ten Change Lens baselines. Identify strengths and barriers. Hold first MicroSummits. Begin Traction Partner matching.

Milestone: M2 - Ten completed baselines and one preliminary cross-site analysis

Weeks 7-10 (Nov): Implement and Learn

Approve ten implementation plans and release activation support. Deliver targeted intervention and coaching. Mobilise Traction Partners. Facilitate cohort peer learning. Begin national-scale modelling.

Milestone: M3 - Ten active implementation cycles with documented evidence

Weeks 11-13 (Dec): Evidence, Cost and Decide

Complete second MicroSummits. Produce cross-site evidence report. Develop the Year 1 LocaeHub model and 500 / 6,000 pathways. Prepare Decision Gate pack and undertake Ministry review.

Milestone: M4 - National Founding Evidence Pack and Year 1 Decision Gate
7. Ten Schools / Ten Counties

The programme proposes one founding school in each of ten different counties to test whether the model remains useful across materially different education environments.

County-selection framework

Major urban

Scale, complexity, mobility and institutional density

Fast-growing peri-urban

Rapid population growth and infrastructure pressure

Coastal

Distinct geographic and community context

Rural agricultural

Distance, local economy and rural access

Arid or semi-arid

Resource constraints and access challenges

Remote / frontier

Distance, staffing and infrastructure constraints

Strong-performing environment

Transferable good practice

Lower-resourced environment

Practical implementation under constraint

Technical / industrial potential

Pathways, STEM and employer relevance

Strong institutional connectivity

Universities, public institutions and partner networks

Initial candidate pool

NairobiKiambuNakuruMombasaKisumuKakamegaUasin GishuMachakosMeruTurkana

School selection criteria

A school is not selected for prestige or ease of access. Each must demonstrate willingness to take part in the full 90-day process.

Senior leadership commitment

Named senior sponsor

Implementation ownership

Named school champion

Evidence participation

Named evidence / data contact

Availability

Able to participate throughout the founding period

Openness

Willingness to identify strengths as well as barriers

Peer-learning potential

Willingness to share learning with other schools

Contextual value

Adds a materially useful context to the cohort

Safeguarding & data readiness

Can meet agreed ethical and data requirements

Sustainability potential

Capacity to embed rather than temporarily host activity

Selection does not constitute inspection, ranking or public judgement of participating schools. Final county and school selection is completed with appropriate Kenyan stakeholders.

Kenyan teacher at a school desk with registers, representing field-based baseline assessment

Change Lens baselines are conducted in the field, in the school's own context.

8. Implementation Methodology

The founding programme is built on five operating principles. Together they define how the eight workstreams are delivered in practice.

Schools as partners, not subjects

Participation is voluntary and collaborative. The programme does not inspect, rank or publicly judge schools.

Need-based support

Support follows identified need from the Change Lens, not a fixed product catalogue.

Peer learning over isolation

Schools learn from each other through MicroSummits and the national cohort, so good practice does not stay trapped in one site.

Evidence before scale

No national expansion is proposed until the founding evidence exists and is reviewed at the Decision Gate.

Sustainability by design

Capability is embedded in schools and future Hubs rather than depending on permanent external intervention.

The methodology is delivered through the Change Lens diagnostic, eight workstreams and MicroSummit peer learning described in the following sections.

9. Change Lens

The Change Lens is the programme's collaborative implementation diagnostic. It is not an inspection. It is completed with each school, not done to it, and it examines ten areas of practice.

Leadership and governance

Vision, governance and implementation capacity

Teacher capability

Confidence, competence and professional development

Teaching and learning

Classroom practice and pedagogy

CBE / CBC implementation

Coverage, sequencing and competency alignment

Competency-based assessment

CBA practice and use of evidence

Inclusion

Equity, access and special needs

Wellbeing

Learner welfare and pastoral support

Family and community

Local understanding and support for CBE

Resources and technology

Equipment, materials, connectivity and digital practice

Pathways, partnerships and sustainability

Institutional links and long-term viability

What each baseline produces

School Context Summary
Strengths Profile
Barrier Profile
One Big Change Priority
Implementation Plan
Capability Requirement
Resource Needs Profile
Evidence Plan
Sustainability Plan

The ten baselines are then combined into one cross-site picture showing what is common, what differs by context, and where good practice already exists.

10. Workstreams

The founding programme operates through nine integrated workstreams, each with a defined primary output.

1

Mobilisation, Governance & Institutional Alignment

Establish the programme infrastructure for lawful, accountable, coordinated implementation: delivery structure, governance, contracting, safeguarding and data protocols, risk management, Advisory Committee and Ministry reporting rhythm.

Output: Inception & Mobilisation Report
2

County and School Selection

Validate county-selection criteria, confirm ten contexts, identify and assess candidate schools, conduct leadership conversations, complete cohort-balance assessment and confirm ten founding schools.

Output: 10 confirmed founding schools across 10 counties
3

School Onboarding & Champion Development

Confirm Senior Sponsors, School Champions and Evidence Contacts. Complete participation agreements, programme orientation, safeguarding and data briefings, Champion induction and digital-platform onboarding.

Output: 10 implementation-ready school teams
4

Change Lens Baselines

A collaborative implementation diagnostic, not an inspection. It examines leadership and governance, teacher capability, teaching and learning, CBE/CBC implementation, competency-based assessment, inclusion, wellbeing, family and community, resources and technology, and pathways, partnerships and sustainability.

Output: 10 quality-assured baselines + one cross-site picture
5

School Implementation Cycles

Each school selects one primary implementation priority and moves through baseline, priority, implementation plan, support and resource, action, evidence, review and next step. Support follows identified need, not a product catalogue.

Output: 10 evidenced implementation cyclesKSh 1.5m activation fund per school
6

MicroSummits & Peer Learning

Two structured MicroSummit moments per school: Understand and Prioritise, then Review and Sustain. The ten schools are connected as one national founding cohort so learning is not trapped in single sites.

Output: 20 MicroSummit moments
7

Traction Partner & Resource Mobilisation

The Change Lens identifies the barrier; the Traction Partner helps remove it. A structured needs-to-resource matrix maps each school need to potential funding, devices, connectivity, software, expertise and infrastructure.

Output: Needs-to-resource matrix
8

Evidence, Research & Learning

Distinguish activity, output, implementation change, early outcome and longer-term impact evidence. Each school holds baseline, implementation, review, limitations and sustainability evidence. No learner-outcome claim is made where the 90-day period or available data is insufficient to support it.

Output: Founding Evidence Report
9

Year 1 National Scale Design

Develop the Year 1 LocaeHub model, the 500-core-school pathway and the 6,000-school connected network, with a full national staffing structure and costed budget.

Output: Year 1 National Implementation Architecture

Ten schools generate the implementation knowledge required to train people, create Hubs, establish systems and replicate the model through controlled national implementation waves.

11. Deliverables and Acceptance Criteria

D1

Inception & Mobilisation Report

Acceptance: Governance, workplan, controls and delivery structure confirmed

D2

Founding Cohort Confirmation

Acceptance: 10 schools in 10 counties

D3

School Participation Pack

Acceptance: Sponsors, Champions, Evidence Contacts and agreements

D4

Change Lens Baseline Pack

Acceptance: 10 quality-assured baselines

D5

Cross-Site Baseline Analysis

Acceptance: Common and contextual patterns identified

D6

School Implementation Portfolio

Acceptance: 10 approved priorities and plans

D7

Implementation Evidence Pack

Acceptance: Evidence from 10 implementation cycles

D8

Traction Partner Needs Matrix

Acceptance: Needs mapped to potential resource routes

D9

Founding Evidence Report

Acceptance: Results, limitations and learning

D10

Hub & Replication Architecture

Acceptance: Proposed Year 1 Hub operating model

D11

Costed Year 1 Programme

Acceptance: National implementation budget

D12

Decision Gate Pack

Acceptance: Recommendation to proceed, modify, extend or stop

12. Results & Performance Framework

The founding phase is considered successful where the programme can demonstrate the following.

MeasureTarget
Counties represented10
Founding schools10
Senior Sponsors10
School Champions10
Evidence Contacts10
Change Lens baselines10
One Big Change priorities10
Implementation plans10
Implementation cycles10
Initial MicroSummits10
Review MicroSummits10
Cross-site analysis1
National needs matrix1
Year 1 architecture1
Year 1 detailed budget1
Government Decision Gate1

The programme separately reports early outcome measures appropriate to each school's selected priority.

Students in a study hall, representing the evidence and assessment dimension of the programme

Every performance target is paired with an evidence requirement. No claim is made without supporting data.

13. Governance and Programme Management

The programme is delivered by a lean founding team with critical Kenya appointments actively under recruitment. Filled roles show current responsibility; vacant roles show the recruitment status of each position.

8

Filled roles

27

Vacant and recruiting

Filled leadership

Y

Yvonne

Global CEO

CEO, Board and Strategy

Board Member
K

Kugan

Global Partnerships and Commercials (CCO)

Funding and Commercial Partnerships

Board Member
J

Jachukwu

Global COO

Executive Leadership

Active
P

Perpetual

Chief of Staff & Kenya Operations Director

Operations and People

Day One
T

Terry

Director of Events, Media & Stakeholder Engagement

Communications, Podcast and Events

Day One
J

Jimmy

Kenya Relations Lead

Kenya Partnerships and Institutional Relations

Active
T

Trinity

People & Volunteer Recruitment Lead

Operations and People

Invited
LA

LocaeRise Admin

Technology Lead

Technology and Systems

Active

Vacant roles under recruitment

Critical Kenya appointments remain subject to formal recruitment and confirmation. Names and roles should not be represented as final Government appointments unless formally contracted.

Country CEO

Country Leadership

Identified

Country COO

Country Leadership

Identified

Country Director of People, Appointments and Institutional Networks

Country Leadership

Identified

Country Senior Education / Implementation Director

Country Leadership

Identified

Kenya Programme Lead

Country Leadership

Identified

Editorial & Content Lead

Communications, Podcast and Events

Identified

Kenya Programme Director

First Project, Programme and Evidence

Recruiting

CBE, CBC and CBA Practice Lead

First Project, Programme and Evidence

Recruiting

School and Hub Implementation Lead

First Project, Programme and Evidence

Recruiting

Evidence, Research and Learning Lead

First Project, Programme and Evidence

Recruiting

Safeguarding, Data and Ethics Lead

Finance, Legal and Governance

Recruiting

Operations, Finance and Grants Coordinator

Operations and People

Recruiting

Hub Programme Coordinator

First Project, Programme and Evidence

Identified

Field Support Officer (Regional)

First Project, Programme and Evidence

Identified

Training & Development Officer

First Project, Programme and Evidence

Identified

Data & Reporting Assistant

First Project, Programme and Evidence

Identified

Monitoring & Evaluation (M&E) Officer

First Project, Programme and Evidence

Identified

Education Research Fellow

First Project, Programme and Evidence

Brief Required

School Liaison Officer

Kenya Partnerships and Institutional Relations

Identified

Partnerships and Programme Intern

Kenya Partnerships and Institutional Relations

Brief Required

Head of Operations and Finance

Operations and People

Identified

Volunteer Onboarding Associate

Operations and People

Identified

HR Administrator

Operations and People

Identified

Office & Admin Assistant

Operations and People

Identified

Procurement & Logistics Officer

Operations and People

Identified

Country Tech Lead

Technology and Systems

Identified

Finance Assistant

Finance, Legal and Governance

Identified

Field Delivery

Local implementation associates and evidence / data support are deployed across the cohort, so national leadership is not expected to personally conduct every activity across ten counties.

14. Ministry and Stakeholder Responsibilities

The programme depends on timely institutional cooperation. One Big Change does not ask public institutions to delegate their statutory or policy responsibilities to the programme.

Ministry / public-institution inputs required

RequirementPurpose
Appropriate institutional sponsorProgramme coordination
Confirmation of relevant policy / technical contactsAlignment
School-selection supportAppropriate access
Participation in inceptionShared expectations
Access to non-confidential policy / implementation informationEvidence alignment
Nomination / engagement with technical institutionsAvoid duplication
Decision Gate participationScale decision
Timely review of contracted deliverablesProgramme continuity

Stakeholder roles

Schools and educators

Co-design, implementation, peer learning and evidence.

Kenyan Advisory Committee

Context, guidance, connections and sustainability.

Universities

Evidence, research and sustainable practice.

Traction Partners

Funding, equipment, technology, expertise and resources.

One Big Change

Framework ownership, coordination, quality assurance and implementation management.

15. Traction Partner Model

The Change Lens identifies need. The Traction Partner mechanism organises the response. A structured needs-to-resource matrix maps each school need to potential funding, devices, connectivity, software, expertise and infrastructure.

Target: KSh 1 billion to KSh 3 billion in additional partner resources mobilised around evidenced school need.

Resource categories mobilised

Devices and connectivitySoftware and platformsSpecialist expertiseResearch and evaluationEquipment and infrastructureFunding for implementation

Traction Partner commitments are recorded separately from Government programme expenditure to ensure transparency over cash and in-kind contributions.

16. Monitoring, Evidence and Learning

The founding programme must produce more than activity reports. Evidence collection combines quantitative and qualitative information appropriate to each school's selected priority.

Baseline

What was happening before intervention?

Intervention

What changed during the founding period?

Implementation evidence

Was the agreed action actually carried out?

Early outcome evidence

What changed for leaders, teachers and learners?

Sustainability evidence

Can practice continue beyond direct programme support?

Context evidence

What explains differences between schools?

No claim of learner-outcome improvement is made where the 90-day period or available data is insufficient to support it.

University of Nairobi graduation, representing evidence, research and learning

The founding programme builds the evidence architecture required for a credible national scale decision.

17. Financial Proposal: KSh 84.37 million

All figures are in Kenyan Shillings. 90-day founding implementation programme.

Budget CategoryAmount (KSh)
Personnel & Programme Leadership23,700,000
Governance, Legal & Assurance5,500,000
Direct School Implementation20,500,000
Travel & Field Logistics6,800,000
Change Lens, Research & Evidence5,500,000
Technology & Data2,500,000
Traction Partner Mobilisation1,500,000
Engagement, Materials & Reporting4,700,000
Year 1 Scale Readiness6,000,000
Subtotal76,700,000
Programme Contingency (10%)7,670,000
TOTAL PROPOSED COMMISSION84,370,000

Note: KSh 15,000,000 is ring-fenced as a School Implementation Activation Fund (KSh 1.5m × 10 schools), released only against approved implementation plans.

Detailed Budget Breakdown

All figures in Kenyan Shillings. Sub-category detail behind the summary total.

A. Personnel & Programme Leadership

23,700,000
  • Kenya Executive Team

    9,000,000

    3 senior roles, ~3.5 months incl. employment / contract provision

  • Operating Leadership

    5,600,000

    4 operational leadership functions, ~3.5 months

  • Founding Directors / Specialist Advisers

    5,600,000

    Up to 6 role-based retainers against agreed deliverables

  • County / Field Implementation Associates

    3,500,000

    Local implementation capacity across the founding cohort

B. Governance, Legal & Assurance

5,500,000
  • Legal & Governance

    2,500,000

    Entity / project structure, agreements, employment / consultancy docs, partner contracting

  • Safeguarding, Data, Compliance & Assurance

    1,500,000

    Data controls, safeguarding framework, compliance review and assurance

  • Finance, Administration & Insurance

    1,500,000

    Financial controls, programme administration, insurance and systems

C. Direct School Implementation

20,500,000
  • 10-School Engagement

    5,500,000

    Onboarding, county liaison, baseline field activity and 20 MicroSummit moments

  • School Implementation Activation Fund

    15,000,000

    Up to KSh 1.5m x 10 schools, released only against approved plans

D. Travel & Field Logistics

6,800,000
  • Ten-County Field Travel

    6,800,000

    Air / road transport, vehicle hire, fuel, accommodation and field subsistence

E. Change Lens, Research & Evidence

5,500,000
  • Change Lens & Evidence

    3,500,000

    Kenya adaptation, champion training, data collection, analysis and synthesis

  • Research / Independent Evaluation Provision

    2,000,000

    Methodology, research input and independent review / evaluation provision

F. Technology & Data

2,500,000
  • Platform & Technology

    2,500,000

    Hosting, platform adaptation, software, dashboards, field-data capability and technical support

G. Traction Partner Mobilisation

1,500,000
  • Traction Partner Activation

    1,500,000

    Partner mapping, propositions, needs matching, due diligence support and roundtables

H. Engagement, Materials & Reporting

4,700,000
  • Field Identification & Programme Materials

    1,000,000

    Clothing / identification, bags, lanyards, notebooks and field materials

  • Volunteer Support and Subsistence

    1,200,000

    Field-day meals and reasonable subsistence for programme volunteers

  • Launch & Decision Gate Events

    1,500,000

    September inception / launch activity and December Decision Gate

  • Reports & Plans

    1,000,000

    10 school plans, national analysis, Year 1 implementation and budget documentation

I. Year 1 Scale Readiness

6,000,000
  • National Scale Architecture

    6,000,000

    50-Hub model, 500-core-school pathway, 6,000-school network design, staffing / resource model and implementation readiness

Subtotal: KSh 76,700,000  +  Contingency (10%): KSh 7,670,000  =  Total: KSh 84,370,000

18. Payment and Milestone Schedule
StageTrigger%Amount (KSh)
Payment 1: MobilisationContract effectiveness, approved inception plan35%29,529,500
Payment 2: Baseline Completion10 schools onboarded, 10 baselines accepted30%25,311,000
Payment 3: Implementation EvidenceImplementation cycles active, interim evidence pack accepted20%16,874,000
Payment 4: Final Decision GateFinal deliverables, Year 1 plan, Decision Gate pack accepted15%12,655,500

No payment milestone constitutes automatic approval of a subsequent national phase. Subject to Government procurement mechanism.

19. Procurement, Financial Control and Value for Money

Expenditure is managed against an approved budget and workplan. Government contracting and procurement follow applicable Kenyan public-procurement requirements.

Financial control principles

  • Designated programme account / cost centre
  • Documented expenditure authority
  • Separation of approval and payment functions
  • Supplier documentation and procurement records
  • School activation-fund controls
  • Asset register where applicable
  • Monthly budget-versus-actual and variance reporting
  • Traction Partner cash / in-kind reporting
  • Conflict-of-interest declarations
  • Independent financial review / audit provision
  • Retention of supporting financial records

Contingency rule

The KSh 7.67 million contingency is not a discretionary spending allocation. It may be applied only to material implementation risks:

  • County travel variance
  • Field logistics
  • Unavoidable programme rescheduling
  • School-access changes
  • Essential specialist support
  • Technology or data requirements
  • Unexpected safeguarding or compliance costs
  • Other approved delivery risks

Use of contingency is documented in programme financial reporting.

20. Risk, Safeguarding, Data and Ethics

Key risks and mitigations

RiskDescriptionMitigation
Delivery delayMobilisation or field access slower than plannedPhased mobilisation, milestone-gated payments, contingency reserve.
School accessCounty or school access changes mid-programmeAlternate candidate schools identified per county; selection criteria.
Data and safeguardingIncomplete consent or data-handling gapsSafeguarding framework, data protocols, champion training before fieldwork.
Evidence limitations90-day period insufficient for outcome claimsNo learner-outcome claim made where data is insufficient; evidence scoped accordingly.
ReputationalMischaracterisation as inspection or rankingClear positioning as collaborative diagnostic; school participation voluntary.

Safeguarding, data and ethics principles

  • School participation is voluntary and collaborative, not compulsory.
  • Data is collected with consent, minimised to programme need and securely stored.
  • No learner-outcome improvement claim is made where the period or data is insufficient.
  • Safeguarding of children and vulnerable adults follows a documented framework.
  • Findings are reported in aggregate; individual schools are not publicly ranked or judged.
A confident Kenyan student in uniform, representing the safeguarding and duty of care at the heart of the programme

Safeguarding, data protection and ethics are not add-ons. They are pre-conditions for fieldwork.

21. December Decision Gate

The December Decision Gate is a genuine decision point. It is not an automatic transition to Year 1. Government and participating stakeholders review the programme against eight criteria:

Relevance

Did the programme address a real implementation need?

Effectiveness

Did schools move from identified barrier to practical action?

Adaptability

Did the model function across different contexts?

Evidence

Are the findings sufficiently credible?

Cost

What did implementation actually cost?

Sustainability

Can schools continue the change?

Additionality

Did the programme add something not already provided by existing structures?

Resource Leverage

Did the model mobilise useful additional capability or resources?

Scale

Can the approach responsibly support a wider national programme?

Possible outcomes

Proceed

Evidence supports Year 1.

Proceed with Modification

Evidence supports scale but requires redesign.

Extend Founding Phase

Promising evidence exists but additional validation is required.

Do Not Scale

Evidence does not justify further public investment.

Government is not asked to commit to the full national programme before the founding evidence exists.

22. Proposed Year 1 National Programme

Subject to a positive Decision Gate, the proposed Year 1 national programme builds from the founding evidence into a structured national architecture.

Year 1 planning assumption

50 LocaeHubs~500 Core Implementation Schools6,000 Connected SchoolsOne National Evidence & Learning NetworkTraction Partner Resource MobilisationLocaeAwardsLocaeFest

Working financial assumption: KSh 1.75 billion + a separately accounted Traction Partner resource pool. The final Year 1 amount is one of the contracted outputs of the 90-day programme, based on actual implementation evidence and cost data.

The three-level scale, Traction Partner model, and LocaeAwards / LocaeFest mechanisms are detailed in the following sections.

Scale is carried by the national programme infrastructure. Not by ten founding schools alone.

23. 50 LocaeHubs / 500 Core Schools / 6,000 Connected Schools

The Year 1 national architecture keeps three levels of ambition clearly separate. The 6,000-school figure is a Year 1 national target, not a 90-day outcome.

50 LocaeHubs

Local implementation and peer-support centres

Each Hub anchors a cluster of schools, hosting workshops, coaching and shared resources.

~500 Core Implementation Schools

Structured implementation cohort

Schools receiving the full Change Lens, implementation support and evidence cycle.

6,000 Connected Schools

National learning and resource network

Schools connected for evidence, communication, peer learning and resource access.

Founding schools receive the deepest diagnostic, implementation and evidence support; the wider network receives connection, learning and resources.

24. LocaeAwards & LocaeFest

Two mechanisms turn individual school progress into shared national learning and recognition. Both are designed into the Year 1 architecture, not added as extras.

LocaeAwards

A recognition mechanism that celebrates evidenced improvement and transferable good practice across the cohort and network. Recognition follows evidence, not publicity.

LocaeFest

A collective learning festival bringing schools, Hubs, partners and communities together to share practice, surface barriers and strengthen the national movement.

Student receiving a certificate of achievement, representing recognition and sustainability

Recognition and sustainability are designed into the model from the founding phase.

25. Sustainability and Exit from Dependency

The programme is explicitly designed to avoid creating permanent dependency on One Big Change. Sustainability is built in from the founding phase, not added at the end.

Embed, don't host

Capability is built into schools and future Hubs so practice continues without permanent external support.

Train-the-trainer

Champions and local associates are equipped to sustain and spread practice beyond the founding period.

Local ownership

Schools and Hubs own their implementation plans, evidence and peer relationships.

Planned exit

Direct programme support is reduced as local capability grows, on a documented exit schedule.

No permanent dependency

The programme is designed to make itself unnecessary at the school level over time.

26. Government Decision Requested

The decision requested

Commission the KSh 84.37 million founding implementation programme for 15 September to 15 December 2026, subject to standard Government procurement and contracting.

Government is not being asked to commit to the full national programme before the founding evidence exists. In return for the founding commission, Government receives:

10 deeply understood school contexts
10 practical implementation cycles
10 school implementation plans
A cross-country picture of barriers and working practice
An evidenced Change Lens methodology
A functioning needs-to-resource mechanism
A tested school-support approach
A proposed LocaeHub model
A 500-core-school implementation architecture
A 6,000-school connection model
A detailed national staffing structure
A full Year 1 budget
A resource-mobilisation proposition
A clear evidence-based decision on whether to scale

Convene an implementation discussion

This proposal is ready for Ministry, procurement, legal and financial scrutiny. We would welcome a conversation.