One Big Change Kenya
National Founding Implementation Programme: a budgeted proposal and implementation plan for Ministry, procurement, legal and financial scrutiny. KSh 84.37 million commission, September-December 2026, ten schools across ten counties.
Kenya has already set the national education direction through Competency-Based Education (CBE), Curriculum (CBC) and Assessment (CBA). The next challenge is not designing policy. It is helping schools with different strengths, circumstances and resources turn that direction into consistent, sustainable practice.
This proposal seeks a KSh 84.37 million founding implementation commission to prove whether the One Big Change model can strengthen practical delivery across 10 materially different Kenyan contexts in 10 different counties.
The 90-day programme runs from 15 September to 15 December 2026. It is deliberately limited in scale. Its purpose is to generate the evidence, delivery architecture and costed plan required for a national Year 1 decision (50 LocaeHubs / 500 Core Schools / 6,000 Connected Schools).
Core purpose
To prove whether the One Big Change implementation model works across different Kenyan contexts, and whether it produces sufficiently robust evidence to justify a national scale decision - before Government is asked to commission national scale.
Programme objectives
Understand barriers
Identify what prevents consistent CBE/CBC/CBA implementation across different school contexts.
Distinguish context
Separate common nationwide barriers from those specific to geography or infrastructure.
Test support mechanisms
Determine which combinations of coaching, development, peer learning and resources change practice.
Build sustainability
Embed capability within schools and future LocaeHubs rather than permanent external intervention.
Design national scale
Define the governance, staffing, funding and infrastructure to move from 10 to 6,000 connected schools.
Produce a costed plan
Deliver an evidenced, costed Year 1 architecture for Government decision at the December Decision Gate.
KSh 84.37M
Total proposed commission
10 schools
Across 10 counties
90 days
15 Sep - 15 Dec 2026
The purpose of this proposal is to secure Government approval to commission a national founding implementation programme.
The founding phase is not a commitment to deliver intensive implementation to 6,000 schools during the first 90 days. Its purpose is to answer a single, vital question before any national scale is considered:
“Does the One Big Change implementation model work across different Kenyan contexts, and does it produce sufficiently robust evidence to justify a national scale decision?”
Kenya has made significant progress in developing Competency-Based Education. However, the challenge of implementation remains. Schools face different combinations of:
- Teacher capability and confidence
- Leadership readiness
- Facilities and specialist equipment
- Technology and connectivity
- Learner wellbeing and inclusion
- Assessment practice
- Family and community understanding
This proposal directly addresses the implementation gap.

The founding programme exists to serve learners across materially different Kenyan contexts.
Policy alignment
Political neutrality
Public procurement compliance
Traction partner leverage
What we are proposing to deliver by 15 December 2026:
- Fully operational Kenyan entity and governance structure.
- Kenyan Advisory Committee in place.
- 10 founding schools selected and onboarded across 10 different counties.
- 10 complete Change Lens baselines and school implementation plans.
- 20 MicroSummit moments delivered (diagnostic and learning).
- National implementation picture (common barriers vs contextual differences).
- Approximately KSh 1.75 billion costed Year 1 national architecture and plan.
1. Understanding barriers
2. Identifying contextual differences
3. Testing support mechanisms
4. Building sustainability
5. Designing national scale
Weeks 1-2 (15-30 Sep): Mobilise and Confirm
Confirm governance and ten schools. Appoint champions and evidence contacts. Train champions, configure Change Lens tools and establish data and safeguarding controls.
Milestone: M1 - 10 schools ready for baselineWeeks 3-6 (Oct): Diagnose & Prioritise
In-person fieldwork in all ten counties. Complete ten Change Lens baselines. Identify strengths and barriers. Hold first MicroSummits. Begin Traction Partner matching.
Milestone: M2 - Ten completed baselines and one preliminary cross-site analysisWeeks 7-10 (Nov): Implement and Learn
Approve ten implementation plans and release activation support. Deliver targeted intervention and coaching. Mobilise Traction Partners. Facilitate cohort peer learning. Begin national-scale modelling.
Milestone: M3 - Ten active implementation cycles with documented evidenceWeeks 11-13 (Dec): Evidence, Cost and Decide
Complete second MicroSummits. Produce cross-site evidence report. Develop the Year 1 LocaeHub model and 500 / 6,000 pathways. Prepare Decision Gate pack and undertake Ministry review.
Milestone: M4 - National Founding Evidence Pack and Year 1 Decision GateThe programme proposes one founding school in each of ten different counties to test whether the model remains useful across materially different education environments.
County-selection framework
Major urban
Scale, complexity, mobility and institutional density
Fast-growing peri-urban
Rapid population growth and infrastructure pressure
Coastal
Distinct geographic and community context
Rural agricultural
Distance, local economy and rural access
Arid or semi-arid
Resource constraints and access challenges
Remote / frontier
Distance, staffing and infrastructure constraints
Strong-performing environment
Transferable good practice
Lower-resourced environment
Practical implementation under constraint
Technical / industrial potential
Pathways, STEM and employer relevance
Strong institutional connectivity
Universities, public institutions and partner networks
Initial candidate pool
School selection criteria
A school is not selected for prestige or ease of access. Each must demonstrate willingness to take part in the full 90-day process.
Senior leadership commitment
Named senior sponsor
Implementation ownership
Named school champion
Evidence participation
Named evidence / data contact
Availability
Able to participate throughout the founding period
Openness
Willingness to identify strengths as well as barriers
Peer-learning potential
Willingness to share learning with other schools
Contextual value
Adds a materially useful context to the cohort
Safeguarding & data readiness
Can meet agreed ethical and data requirements
Sustainability potential
Capacity to embed rather than temporarily host activity
Selection does not constitute inspection, ranking or public judgement of participating schools. Final county and school selection is completed with appropriate Kenyan stakeholders.

Change Lens baselines are conducted in the field, in the school's own context.
The founding programme is built on five operating principles. Together they define how the eight workstreams are delivered in practice.
Schools as partners, not subjects
Participation is voluntary and collaborative. The programme does not inspect, rank or publicly judge schools.
Need-based support
Support follows identified need from the Change Lens, not a fixed product catalogue.
Peer learning over isolation
Schools learn from each other through MicroSummits and the national cohort, so good practice does not stay trapped in one site.
Evidence before scale
No national expansion is proposed until the founding evidence exists and is reviewed at the Decision Gate.
Sustainability by design
Capability is embedded in schools and future Hubs rather than depending on permanent external intervention.
The methodology is delivered through the Change Lens diagnostic, eight workstreams and MicroSummit peer learning described in the following sections.
The Change Lens is the programme's collaborative implementation diagnostic. It is not an inspection. It is completed with each school, not done to it, and it examines ten areas of practice.
Leadership and governance
Vision, governance and implementation capacity
Teacher capability
Confidence, competence and professional development
Teaching and learning
Classroom practice and pedagogy
CBE / CBC implementation
Coverage, sequencing and competency alignment
Competency-based assessment
CBA practice and use of evidence
Inclusion
Equity, access and special needs
Wellbeing
Learner welfare and pastoral support
Family and community
Local understanding and support for CBE
Resources and technology
Equipment, materials, connectivity and digital practice
Pathways, partnerships and sustainability
Institutional links and long-term viability
What each baseline produces
The ten baselines are then combined into one cross-site picture showing what is common, what differs by context, and where good practice already exists.
The founding programme operates through nine integrated workstreams, each with a defined primary output.
Mobilisation, Governance & Institutional Alignment
Establish the programme infrastructure for lawful, accountable, coordinated implementation: delivery structure, governance, contracting, safeguarding and data protocols, risk management, Advisory Committee and Ministry reporting rhythm.
County and School Selection
Validate county-selection criteria, confirm ten contexts, identify and assess candidate schools, conduct leadership conversations, complete cohort-balance assessment and confirm ten founding schools.
School Onboarding & Champion Development
Confirm Senior Sponsors, School Champions and Evidence Contacts. Complete participation agreements, programme orientation, safeguarding and data briefings, Champion induction and digital-platform onboarding.
Change Lens Baselines
A collaborative implementation diagnostic, not an inspection. It examines leadership and governance, teacher capability, teaching and learning, CBE/CBC implementation, competency-based assessment, inclusion, wellbeing, family and community, resources and technology, and pathways, partnerships and sustainability.
School Implementation Cycles
Each school selects one primary implementation priority and moves through baseline, priority, implementation plan, support and resource, action, evidence, review and next step. Support follows identified need, not a product catalogue.
MicroSummits & Peer Learning
Two structured MicroSummit moments per school: Understand and Prioritise, then Review and Sustain. The ten schools are connected as one national founding cohort so learning is not trapped in single sites.
Traction Partner & Resource Mobilisation
The Change Lens identifies the barrier; the Traction Partner helps remove it. A structured needs-to-resource matrix maps each school need to potential funding, devices, connectivity, software, expertise and infrastructure.
Evidence, Research & Learning
Distinguish activity, output, implementation change, early outcome and longer-term impact evidence. Each school holds baseline, implementation, review, limitations and sustainability evidence. No learner-outcome claim is made where the 90-day period or available data is insufficient to support it.
Year 1 National Scale Design
Develop the Year 1 LocaeHub model, the 500-core-school pathway and the 6,000-school connected network, with a full national staffing structure and costed budget.
Ten schools generate the implementation knowledge required to train people, create Hubs, establish systems and replicate the model through controlled national implementation waves.
D1
Inception & Mobilisation Report
Acceptance: Governance, workplan, controls and delivery structure confirmed
D2
Founding Cohort Confirmation
Acceptance: 10 schools in 10 counties
D3
School Participation Pack
Acceptance: Sponsors, Champions, Evidence Contacts and agreements
D4
Change Lens Baseline Pack
Acceptance: 10 quality-assured baselines
D5
Cross-Site Baseline Analysis
Acceptance: Common and contextual patterns identified
D6
School Implementation Portfolio
Acceptance: 10 approved priorities and plans
D7
Implementation Evidence Pack
Acceptance: Evidence from 10 implementation cycles
D8
Traction Partner Needs Matrix
Acceptance: Needs mapped to potential resource routes
D9
Founding Evidence Report
Acceptance: Results, limitations and learning
D10
Hub & Replication Architecture
Acceptance: Proposed Year 1 Hub operating model
D11
Costed Year 1 Programme
Acceptance: National implementation budget
D12
Decision Gate Pack
Acceptance: Recommendation to proceed, modify, extend or stop
The founding phase is considered successful where the programme can demonstrate the following.
| Measure | Target |
|---|---|
| Counties represented | 10 |
| Founding schools | 10 |
| Senior Sponsors | 10 |
| School Champions | 10 |
| Evidence Contacts | 10 |
| Change Lens baselines | 10 |
| One Big Change priorities | 10 |
| Implementation plans | 10 |
| Implementation cycles | 10 |
| Initial MicroSummits | 10 |
| Review MicroSummits | 10 |
| Cross-site analysis | 1 |
| National needs matrix | 1 |
| Year 1 architecture | 1 |
| Year 1 detailed budget | 1 |
| Government Decision Gate | 1 |
The programme separately reports early outcome measures appropriate to each school's selected priority.

Every performance target is paired with an evidence requirement. No claim is made without supporting data.
The programme is delivered by a lean founding team with critical Kenya appointments actively under recruitment. Filled roles show current responsibility; vacant roles show the recruitment status of each position.
8
Filled roles
27
Vacant and recruiting
Filled leadership
Yvonne
Global CEO
CEO, Board and Strategy
Board MemberKugan
Global Partnerships and Commercials (CCO)
Funding and Commercial Partnerships
Board MemberJachukwu
Global COO
Executive Leadership
ActivePerpetual
Chief of Staff & Kenya Operations Director
Operations and People
Day OneTerry
Director of Events, Media & Stakeholder Engagement
Communications, Podcast and Events
Day OneJimmy
Kenya Relations Lead
Kenya Partnerships and Institutional Relations
ActiveTrinity
People & Volunteer Recruitment Lead
Operations and People
InvitedLocaeRise Admin
Technology Lead
Technology and Systems
ActiveVacant roles under recruitment
Critical Kenya appointments remain subject to formal recruitment and confirmation. Names and roles should not be represented as final Government appointments unless formally contracted.
Country CEO
Country Leadership
IdentifiedCountry COO
Country Leadership
IdentifiedCountry Director of People, Appointments and Institutional Networks
Country Leadership
IdentifiedCountry Senior Education / Implementation Director
Country Leadership
IdentifiedKenya Programme Lead
Country Leadership
IdentifiedEditorial & Content Lead
Communications, Podcast and Events
IdentifiedKenya Programme Director
First Project, Programme and Evidence
RecruitingCBE, CBC and CBA Practice Lead
First Project, Programme and Evidence
RecruitingSchool and Hub Implementation Lead
First Project, Programme and Evidence
RecruitingEvidence, Research and Learning Lead
First Project, Programme and Evidence
RecruitingSafeguarding, Data and Ethics Lead
Finance, Legal and Governance
RecruitingOperations, Finance and Grants Coordinator
Operations and People
RecruitingHub Programme Coordinator
First Project, Programme and Evidence
IdentifiedField Support Officer (Regional)
First Project, Programme and Evidence
IdentifiedTraining & Development Officer
First Project, Programme and Evidence
IdentifiedData & Reporting Assistant
First Project, Programme and Evidence
IdentifiedMonitoring & Evaluation (M&E) Officer
First Project, Programme and Evidence
IdentifiedEducation Research Fellow
First Project, Programme and Evidence
Brief RequiredSchool Liaison Officer
Kenya Partnerships and Institutional Relations
IdentifiedPartnerships and Programme Intern
Kenya Partnerships and Institutional Relations
Brief RequiredHead of Operations and Finance
Operations and People
IdentifiedVolunteer Onboarding Associate
Operations and People
IdentifiedHR Administrator
Operations and People
IdentifiedOffice & Admin Assistant
Operations and People
IdentifiedProcurement & Logistics Officer
Operations and People
IdentifiedCountry Tech Lead
Technology and Systems
IdentifiedFinance Assistant
Finance, Legal and Governance
IdentifiedField Delivery
Local implementation associates and evidence / data support are deployed across the cohort, so national leadership is not expected to personally conduct every activity across ten counties.
The programme depends on timely institutional cooperation. One Big Change does not ask public institutions to delegate their statutory or policy responsibilities to the programme.
Ministry / public-institution inputs required
| Requirement | Purpose |
|---|---|
| Appropriate institutional sponsor | Programme coordination |
| Confirmation of relevant policy / technical contacts | Alignment |
| School-selection support | Appropriate access |
| Participation in inception | Shared expectations |
| Access to non-confidential policy / implementation information | Evidence alignment |
| Nomination / engagement with technical institutions | Avoid duplication |
| Decision Gate participation | Scale decision |
| Timely review of contracted deliverables | Programme continuity |
Stakeholder roles
Schools and educators
Co-design, implementation, peer learning and evidence.
Kenyan Advisory Committee
Context, guidance, connections and sustainability.
Universities
Evidence, research and sustainable practice.
Traction Partners
Funding, equipment, technology, expertise and resources.
One Big Change
Framework ownership, coordination, quality assurance and implementation management.
The Change Lens identifies need. The Traction Partner mechanism organises the response. A structured needs-to-resource matrix maps each school need to potential funding, devices, connectivity, software, expertise and infrastructure.
Target: KSh 1 billion to KSh 3 billion in additional partner resources mobilised around evidenced school need.
Resource categories mobilised
Traction Partner commitments are recorded separately from Government programme expenditure to ensure transparency over cash and in-kind contributions.
The founding programme must produce more than activity reports. Evidence collection combines quantitative and qualitative information appropriate to each school's selected priority.
Baseline
What was happening before intervention?
Intervention
What changed during the founding period?
Implementation evidence
Was the agreed action actually carried out?
Early outcome evidence
What changed for leaders, teachers and learners?
Sustainability evidence
Can practice continue beyond direct programme support?
Context evidence
What explains differences between schools?
No claim of learner-outcome improvement is made where the 90-day period or available data is insufficient to support it.

The founding programme builds the evidence architecture required for a credible national scale decision.
All figures are in Kenyan Shillings. 90-day founding implementation programme.
| Budget Category | Amount (KSh) |
|---|---|
| Personnel & Programme Leadership | 23,700,000 |
| Governance, Legal & Assurance | 5,500,000 |
| Direct School Implementation | 20,500,000 |
| Travel & Field Logistics | 6,800,000 |
| Change Lens, Research & Evidence | 5,500,000 |
| Technology & Data | 2,500,000 |
| Traction Partner Mobilisation | 1,500,000 |
| Engagement, Materials & Reporting | 4,700,000 |
| Year 1 Scale Readiness | 6,000,000 |
| Subtotal | 76,700,000 |
| Programme Contingency (10%) | 7,670,000 |
| TOTAL PROPOSED COMMISSION | 84,370,000 |
Note: KSh 15,000,000 is ring-fenced as a School Implementation Activation Fund (KSh 1.5m × 10 schools), released only against approved implementation plans.
All figures in Kenyan Shillings. Sub-category detail behind the summary total.
A. Personnel & Programme Leadership
23,700,000Kenya Executive Team
9,000,000
3 senior roles, ~3.5 months incl. employment / contract provision
Operating Leadership
5,600,000
4 operational leadership functions, ~3.5 months
Founding Directors / Specialist Advisers
5,600,000
Up to 6 role-based retainers against agreed deliverables
County / Field Implementation Associates
3,500,000
Local implementation capacity across the founding cohort
B. Governance, Legal & Assurance
5,500,000Legal & Governance
2,500,000
Entity / project structure, agreements, employment / consultancy docs, partner contracting
Safeguarding, Data, Compliance & Assurance
1,500,000
Data controls, safeguarding framework, compliance review and assurance
Finance, Administration & Insurance
1,500,000
Financial controls, programme administration, insurance and systems
C. Direct School Implementation
20,500,00010-School Engagement
5,500,000
Onboarding, county liaison, baseline field activity and 20 MicroSummit moments
School Implementation Activation Fund
15,000,000
Up to KSh 1.5m x 10 schools, released only against approved plans
D. Travel & Field Logistics
6,800,000Ten-County Field Travel
6,800,000
Air / road transport, vehicle hire, fuel, accommodation and field subsistence
E. Change Lens, Research & Evidence
5,500,000Change Lens & Evidence
3,500,000
Kenya adaptation, champion training, data collection, analysis and synthesis
Research / Independent Evaluation Provision
2,000,000
Methodology, research input and independent review / evaluation provision
F. Technology & Data
2,500,000Platform & Technology
2,500,000
Hosting, platform adaptation, software, dashboards, field-data capability and technical support
G. Traction Partner Mobilisation
1,500,000Traction Partner Activation
1,500,000
Partner mapping, propositions, needs matching, due diligence support and roundtables
H. Engagement, Materials & Reporting
4,700,000Field Identification & Programme Materials
1,000,000
Clothing / identification, bags, lanyards, notebooks and field materials
Volunteer Support and Subsistence
1,200,000
Field-day meals and reasonable subsistence for programme volunteers
Launch & Decision Gate Events
1,500,000
September inception / launch activity and December Decision Gate
Reports & Plans
1,000,000
10 school plans, national analysis, Year 1 implementation and budget documentation
I. Year 1 Scale Readiness
6,000,000National Scale Architecture
6,000,000
50-Hub model, 500-core-school pathway, 6,000-school network design, staffing / resource model and implementation readiness
Subtotal: KSh 76,700,000 + Contingency (10%): KSh 7,670,000 = Total: KSh 84,370,000
| Stage | Trigger | % | Amount (KSh) |
|---|---|---|---|
| Payment 1: Mobilisation | Contract effectiveness, approved inception plan | 35% | 29,529,500 |
| Payment 2: Baseline Completion | 10 schools onboarded, 10 baselines accepted | 30% | 25,311,000 |
| Payment 3: Implementation Evidence | Implementation cycles active, interim evidence pack accepted | 20% | 16,874,000 |
| Payment 4: Final Decision Gate | Final deliverables, Year 1 plan, Decision Gate pack accepted | 15% | 12,655,500 |
No payment milestone constitutes automatic approval of a subsequent national phase. Subject to Government procurement mechanism.
Expenditure is managed against an approved budget and workplan. Government contracting and procurement follow applicable Kenyan public-procurement requirements.
Financial control principles
- Designated programme account / cost centre
- Documented expenditure authority
- Separation of approval and payment functions
- Supplier documentation and procurement records
- School activation-fund controls
- Asset register where applicable
- Monthly budget-versus-actual and variance reporting
- Traction Partner cash / in-kind reporting
- Conflict-of-interest declarations
- Independent financial review / audit provision
- Retention of supporting financial records
Contingency rule
The KSh 7.67 million contingency is not a discretionary spending allocation. It may be applied only to material implementation risks:
- County travel variance
- Field logistics
- Unavoidable programme rescheduling
- School-access changes
- Essential specialist support
- Technology or data requirements
- Unexpected safeguarding or compliance costs
- Other approved delivery risks
Use of contingency is documented in programme financial reporting.
Key risks and mitigations
| Risk | Description | Mitigation |
|---|---|---|
| Delivery delay | Mobilisation or field access slower than planned | Phased mobilisation, milestone-gated payments, contingency reserve. |
| School access | County or school access changes mid-programme | Alternate candidate schools identified per county; selection criteria. |
| Data and safeguarding | Incomplete consent or data-handling gaps | Safeguarding framework, data protocols, champion training before fieldwork. |
| Evidence limitations | 90-day period insufficient for outcome claims | No learner-outcome claim made where data is insufficient; evidence scoped accordingly. |
| Reputational | Mischaracterisation as inspection or ranking | Clear positioning as collaborative diagnostic; school participation voluntary. |
Safeguarding, data and ethics principles
- School participation is voluntary and collaborative, not compulsory.
- Data is collected with consent, minimised to programme need and securely stored.
- No learner-outcome improvement claim is made where the period or data is insufficient.
- Safeguarding of children and vulnerable adults follows a documented framework.
- Findings are reported in aggregate; individual schools are not publicly ranked or judged.

Safeguarding, data protection and ethics are not add-ons. They are pre-conditions for fieldwork.
The December Decision Gate is a genuine decision point. It is not an automatic transition to Year 1. Government and participating stakeholders review the programme against eight criteria:
Relevance
Did the programme address a real implementation need?
Effectiveness
Did schools move from identified barrier to practical action?
Adaptability
Did the model function across different contexts?
Evidence
Are the findings sufficiently credible?
Cost
What did implementation actually cost?
Sustainability
Can schools continue the change?
Additionality
Did the programme add something not already provided by existing structures?
Resource Leverage
Did the model mobilise useful additional capability or resources?
Scale
Can the approach responsibly support a wider national programme?
Possible outcomes
Proceed
Evidence supports Year 1.
Proceed with Modification
Evidence supports scale but requires redesign.
Extend Founding Phase
Promising evidence exists but additional validation is required.
Do Not Scale
Evidence does not justify further public investment.
Government is not asked to commit to the full national programme before the founding evidence exists.
Subject to a positive Decision Gate, the proposed Year 1 national programme builds from the founding evidence into a structured national architecture.
Year 1 planning assumption
Working financial assumption: KSh 1.75 billion + a separately accounted Traction Partner resource pool. The final Year 1 amount is one of the contracted outputs of the 90-day programme, based on actual implementation evidence and cost data.
The three-level scale, Traction Partner model, and LocaeAwards / LocaeFest mechanisms are detailed in the following sections.
Scale is carried by the national programme infrastructure. Not by ten founding schools alone.
The Year 1 national architecture keeps three levels of ambition clearly separate. The 6,000-school figure is a Year 1 national target, not a 90-day outcome.
50 LocaeHubs
Local implementation and peer-support centresEach Hub anchors a cluster of schools, hosting workshops, coaching and shared resources.
~500 Core Implementation Schools
Structured implementation cohortSchools receiving the full Change Lens, implementation support and evidence cycle.
6,000 Connected Schools
National learning and resource networkSchools connected for evidence, communication, peer learning and resource access.
Founding schools receive the deepest diagnostic, implementation and evidence support; the wider network receives connection, learning and resources.
Two mechanisms turn individual school progress into shared national learning and recognition. Both are designed into the Year 1 architecture, not added as extras.
LocaeAwards
A recognition mechanism that celebrates evidenced improvement and transferable good practice across the cohort and network. Recognition follows evidence, not publicity.
LocaeFest
A collective learning festival bringing schools, Hubs, partners and communities together to share practice, surface barriers and strengthen the national movement.

Recognition and sustainability are designed into the model from the founding phase.
The programme is explicitly designed to avoid creating permanent dependency on One Big Change. Sustainability is built in from the founding phase, not added at the end.
Embed, don't host
Capability is built into schools and future Hubs so practice continues without permanent external support.
Train-the-trainer
Champions and local associates are equipped to sustain and spread practice beyond the founding period.
Local ownership
Schools and Hubs own their implementation plans, evidence and peer relationships.
Planned exit
Direct programme support is reduced as local capability grows, on a documented exit schedule.
No permanent dependency
The programme is designed to make itself unnecessary at the school level over time.
The decision requested
Commission the KSh 84.37 million founding implementation programme for 15 September to 15 December 2026, subject to standard Government procurement and contracting.
Government is not being asked to commit to the full national programme before the founding evidence exists. In return for the founding commission, Government receives:
The appendices provide the technical detail behind every number and promise on this page. Each is available for the relevant scrutiny function: finance, education, procurement, legal or governance.
Appendix 1
90-Day Founding Implementation Plan & Detailed Budget
Open appendixAppendix 2
Results, Outcomes, KPIs & Ministry Performance Framework
Open appendixAppendix 3
Governance, Leadership & RACI
Open appendixAppendix 4
County, School Selection & Change Lens Methodology
Open appendixAppendix 5
Monitoring, Evaluation, Evidence & Learning
Open appendixAppendix 6
Risk, Safeguarding, Data & Ethics
Open appendixAppendix 7
Traction Partner & Resource Mobilisation
Open appendixAppendix 8
Year 1: 50 Hubs / 500 Core / 6,000 Connected
Open appendixAppendix 9
Procurement, Financial Controls & Value for Money
Open appendixAppendix 10
Evidence Base & Sources
Open appendixConvene an implementation discussion
This proposal is ready for Ministry, procurement, legal and financial scrutiny. We would welcome a conversation.