Appendix 9

Financial Controls, Procurement & Value for Money

The financial-management, procurement, expenditure-control, audit, reporting and value-for-money architecture for One Big Change Kenya - carefully distinguishing the Government's procurement of One Big Change from One Big Change's management of programme funds after contracting. One Big Change Kenya, 2026.

1. Purpose of this Appendix

This Appendix sets out the proposed financial-management, procurement, expenditure-control, audit, reporting and value-for-money architecture for the One Big Change Kenya programme.

Its purpose is to establish how programme resources will be:

  • authorised
  • received
  • budgeted
  • committed
  • procured
  • spent
  • documented
  • monitored
  • reconciled
  • reported
  • audited
  • protected from misuse
  • connected to contracted outputs and outcomes

The framework applies first to the proposed 90-day Founding Implementation Programme and establishes the controls that would need to mature further before any Year 1 national programme is commissioned.

2. Core Financial Principle
Money follows an approved purpose, an authorised budget, an evidenced need, an accountable owner and a verifiable result.

No programme expenditure should exist simply because budget remains available.

Every material expenditure should be capable of answering:

1Why was it required?
2Which approved budget line authorised it?
3Who approved it?
4How was the supplier or recipient selected?
5What was received?
6What evidence supports the payment?
7Which programme output or outcome did it support?
8Where is the audit trail?
3. Government Procurement and Programme Delivery Are Distinct

Two financial-control environments must be distinguished.

Stage A

Government Procurement of One Big Change

The relevant Government/public entity determines the lawful procurement and contracting mechanism. Its responsibilities include matters such as:

  • approved budget
  • procurement planning
  • procurement method
  • tender/RFP documentation
  • evaluation
  • award
  • contract execution
  • contract management
  • payment approval

One Big Change must not determine Government's procurement route for Government.

Stage B

One Big Change Programme Financial Management

Once a lawful contract is in force, One Big Change becomes responsible for delivering the contracted programme according to:

  • the signed contract
  • approved budget
  • agreed deliverables
  • applicable law
  • programme financial controls
  • supplier and subcontractor requirements
  • audit and reporting obligations

The precise treatment of programme funds, subcontracting obligations and any additional public-sector requirements will be confirmed in the final Government contract and through Kenyan legal and financial advice.

4. No Assumption of Automatic Fund Release

Approval of this proposal does not by itself constitute authority for expenditure. Funding can only be drawn through the lawful Government process and the executed contract.

The programme therefore distinguishes:

Proposal approval

↓

procurement award

↓

contract execution

↓

milestone acceptance

↓

payment authorisation

↓

cash receipt

5. Public Procurement Principles

Where the relevant public entity procures the programme, the applicable Kenyan public-procurement framework applies. The current PPADA framework gives effect to the constitutional requirement for public procurement to operate through a system that is fair, equitable, transparent, competitive and cost-effective.

One Big Change's proposal will therefore be structured so that its:

  • scope
  • deliverables
  • evaluation criteria
  • milestones
  • costs
  • reporting
  • acceptance criteria

can be converted into a formal procurement and contract-management structure if required.

6. Procurement Route

This proposal does not prescribe the procurement method Government must use. The appropriate route will be determined by the relevant public entity based on:

  • applicable law
  • procurement plan
  • approved budget
  • nature of the requirement
  • value
  • timing
  • technical characteristics
  • lawful procurement method

One Big Change will provide the technical and commercial information necessary to support that process.

7. Procurement Planning

The Government-facing programme should be capable of being translated into an identifiable procurement requirement. The procurement requirement should specify:

  • programme objective
  • implementation period
  • technical scope
  • geographic scope
  • deliverables
  • performance measures
  • evidence requirements
  • reporting
  • budget
  • payment milestones
  • contract-management requirements
8. No Contract Splitting

Programme requirements must not be artificially divided for the purpose of avoiding an applicable procurement process or threshold.

The programme should be packaged according to genuine operational need rather than an artificial attempt to circumvent procurement requirements.
9. One Big Change Procurement Plan

Following contract award, One Big Change will maintain its own Programme Procurement Plan. The plan should identify expected procurement such as:

  • technology
  • travel
  • venues
  • research/evaluation
  • expert services
  • equipment
  • communications
  • legal services
  • insurance
  • field services
  • implementation resources
  • events

For each planned procurement it should record:

  • requirement
  • budget
  • expected date
  • procurement approach
  • approving authority
  • responsible person
10. Procurement Categories

Programme purchases should be categorised into:

Goods

Physical items and equipment.

Professional Services

Specialist professional capability.

Non-Consulting Services

Operational or routine services.

Technology

Software, platforms, hosting and technical services.

Works

Any physical works or installations, if applicable.

Travel and Logistics

Transport, accommodation and field operations.

School Implementation Resources

Goods or services required under approved school implementation plans.

Classification helps determine the appropriate procurement process.

11. Segregation of Duties

The programme will maintain separation between critical financial functions. Where practicable, different people should undertake:

Request

↓

Approval

↓

Procurement

↓

Receipt confirmation

↓

Payment

↓

Reconciliation

12. Minimum Financial Roles

The programme should maintain the following functions.

Budget Holder

Responsible for the relevant budget.

Requester

Identifies the legitimate programme need.

Procurement / Sourcing Function

Conducts the sourcing process.

Approver

Approves commitment/expenditure within delegated authority.

Receiver / Technical Verifier

Confirms the good or service has been received satisfactorily.

Finance Function

Processes payment and maintains accounting records.

Reviewer / Reconciler

Checks transactions and reconciliations.

No single person should control the entire transaction cycle for material expenditure.

13. Delegated Financial Authority

Before mobilisation, a formal Delegated Financial Authority Schedule will be approved. It should specify who can approve:

  • recruitment
  • consultancy
  • supplier engagement
  • purchase orders
  • travel
  • school activation expenditure
  • contract variations
  • contingency use
  • asset purchases
  • payments

Authority should increase with seniority and transaction value.

14. Financial Authority Principle

A person's seniority does not provide unlimited spending authority. The Founder, Kenya CEO, directors and programme staff remain subject to the approved financial-control framework.

No individual should approve their own:

  • invoice
  • expense claim
  • consultancy payment
  • supplier relationship
  • reimbursement
15. Founding Programme Budget

The indicative founding budget is:

CategoryAmount
Personnel & Programme LeadershipKSh 23,700,000
Governance, Legal & AssuranceKSh 5,500,000
Direct School ImplementationKSh 20,500,000
Travel & Field LogisticsKSh 6,800,000
Change Lens, Research & EvidenceKSh 5,500,000
Technology & DataKSh 2,500,000
Traction Partner MobilisationKSh 1,500,000
Engagement, Materials & ReportingKSh 4,700,000
Year 1 Scale ReadinessKSh 6,000,000
SubtotalKSh 76,700,000
Programme ContingencyKSh 7,670,000
TotalKSh 84,370,000

This budget remains subject to validation during contracting.

16. Budget Control

Every expenditure must map to an approved:

  • programme
  • workstream
  • budget line
  • cost centre
  • activity

The finance system should permit reporting by:

  • category
  • workstream
  • school
  • county
  • supplier
  • Hub where applicable
  • funding source
17. Budget Versus Actual

Finance will produce a monthly Budget Versus Actual report. The report should show:

  • approved budget
  • spend to date
  • committed spend
  • remaining budget
  • forecast final cost
  • variance
  • variance explanation

Material unexplained variance should trigger review.

18. Commitment Accounting

Programme management should not treat unspent bank cash as available simply because an invoice has not yet been paid. The programme should track:

Paid

Already disbursed.

Committed

Contractually committed but unpaid.

Forecast

Expected future expenditure.

Available

Budget genuinely available after commitments.

This prevents accidental overspending.

19. Cash-Flow Management

The programme should maintain a rolling cash-flow forecast covering at least:

  • payroll
  • contracted suppliers
  • school implementation
  • travel
  • tax
  • technology
  • events
  • professional services
  • contingency
Cash-flow pressure must not be solved by using restricted programme money for unrelated purposes.
20. Programme Banking

Where appropriate to the final contracting model, programme funds should be identifiable through:

dedicated project account

clearly segregated project ledger/cost centre

The final approach will depend on contract terms, legal structure, banking arrangements and accounting requirements.

The overriding requirement is traceability.

21. Payment Milestones

The proposed founding payment structure remains:

PaymentTrigger%Amount
1Contract effectiveness and accepted inception/mobilisation requirements35%KSh 29,529,500
210 schools onboarded and baseline deliverables accepted30%KSh 25,311,000
3Implementation cycles active and interim evidence accepted20%KSh 16,874,000
4Final deliverables and Decision Gate pack accepted15%KSh 12,655,500
Total100%KSh 84,370,000

The final contract may vary this schedule.

22. Payment Is Linked to Acceptance

Payment should not depend solely on the passage of time. Each contractual milestone should identify:

  • deliverable
  • completion standard
  • evidence
  • submission date
  • Government review period
  • acceptance
  • correction mechanism
  • invoice point
23. Deliverable Acceptance

For example:

Activity

Visit ten schools.

This alone should not trigger acceptance.

Deliverable

Ten quality-assured Change Lens baselines meeting the agreed standard.

That is capable of contractual verification.

Financial milestones should therefore follow deliverables rather than activity counts wherever practical.

24. Invoice Control

Before an invoice is submitted to Government, One Big Change should confirm:

  • milestone achieved
  • required deliverables submitted
  • acceptance evidence available
  • invoice matches contract
  • taxes treated correctly
  • supporting information complete
25. Tax Treatment

The final financial proposal should state clearly whether figures are:

  • inclusive of applicable taxes
  • exclusive of applicable taxes
  • subject to withholding or other statutory treatment

The precise Kenyan tax treatment must be validated before contract signature by appropriately qualified Kenyan tax/accounting advisers.

The KSh 84.37 million figure should therefore not be represented as a final tax-inclusive contractual amount until this validation has occurred.
26. Supplier Onboarding

Before material payment to a supplier, the programme should normally hold:

  • legal name
  • registration details
  • tax information where required
  • bank details
  • contact details
  • contract/purchase order
  • ownership/beneficial ownership information where appropriate
  • conflict declaration where relevant
27. Supplier Due Diligence

Due diligence should be proportionate to:

  • value
  • risk
  • school access
  • child contact
  • data access
  • reputation
  • financial exposure

Higher-risk suppliers require deeper checks.

28. Competitive Sourcing

Where appropriate, the programme should compare more than one credible supplier. Comparison may consider:

  • price
  • quality
  • delivery
  • expertise
  • sustainability
  • total cost
  • school suitability
  • safeguarding
  • data security

Lowest price alone does not necessarily represent best value.

29. Single-Source Procurement

Where only one provider is realistically suitable, the file should record:

  • reason
  • market evidence
  • uniqueness
  • price justification
  • conflict review
  • approval

Convenience is not in itself sufficient justification.

30. Market Testing

For significant purchases, the programme should obtain reasonable evidence that cost is appropriate. This may include:

  • quotations
  • market research
  • benchmark pricing
  • historic comparable cost
  • independent estimate
31. Purchase Order / Contract First

Material expenditure should not routinely proceed on a retrospective basis. The intended sequence is:

Need

↓

Approval

↓

Supplier selection

↓

Purchase order / contract

↓

Delivery

↓

Verification

↓

Invoice

↓

Payment

32. Three-Way Match

Where appropriate, payment should require matching:

1

Purchase Order / Contract

2

Proof of Receipt / Acceptance

3

Supplier Invoice

Material discrepancies must be resolved before payment.

33. Goods Receipt

Physical goods should be verified for:

  • quantity
  • specification
  • condition
  • delivery location
  • serial/asset number where relevant

Receipt should be recorded by a person independent of the supplier.

34. Services Acceptance

Professional or contracted services should be accepted against:

  • agreed scope
  • deliverable
  • timescale
  • quality standard
  • evidence of completion
A consultant's invoice is not itself evidence that the work was delivered.
35. School Activation Fund

The proposed founding programme contains:

KSh 15,000,000

School Implementation Activation

Up to KSh 1.5m

Per founding school (average)

This is an average planning envelope but is not an automatic unrestricted transfer.

36. Activation Fund Conditions

Expenditure should require:

1completed Change Lens
2identified priority
3school implementation plan
4specific resource requirement
5cost estimate
6programme approval
7appropriate sourcing
8evidence of delivery
9evidence of implementation
37. School Funding Should Follow Need

One founding school may require:

KSh 500,000

One school

KSh 1.4 million

Another school

Expert support

Rather than equipment

The portfolio budget must therefore remain needs-led rather than forcing equal expenditure.

38. Unused School Allocation

Unused school activation funding remains programme funding.

It should not be spent merely to ensure that every school's theoretical allocation is exhausted.
39. Direct Purchase vs School Transfer

Where practical, the programme may procure required goods/services directly rather than transferring cash to schools.

Where cash transfer is appropriate, additional controls should specify:

  • purpose
  • amount
  • account
  • authorised recipient
  • reporting
  • evidence
  • return of unspent funds
  • audit rights

The lawful mechanism must be agreed before use.

40. School Asset Register

Where significant assets are acquired, records should identify:

  • description
  • serial number
  • value
  • funding source
  • date
  • location
  • custodian
  • ownership
  • maintenance responsibility
41. Asset Ownership

Programme documents must distinguish between:

Government-owned assets
One Big Change-owned assets
school-owned assets
Traction Partner-owned/loaned assets

Ownership should never be inferred merely from physical possession.

42. Asset Handover

Where assets are formally transferred to a school or public institution, the transfer should be documented. The documentation should establish:

  • asset
  • condition
  • value
  • receiving organisation
  • responsible officer
  • maintenance expectations
43. Travel Control

Travel expenditure should require:

  • programme purpose
  • approved itinerary
  • traveller
  • county/school
  • cost estimate
  • authorisation

Travel should be consolidated where possible to reduce cost.

44. Travel Value for Money

The ten-county founding design increases logistics costs. The programme should therefore track:

  • cost per field mission
  • cost per county
  • cost per school
  • team size
  • number of useful programme outputs per visit

This evidence will determine the Year 1 mix of:

  • national travel
  • cluster delivery
  • Hub delivery
  • digital delivery
45. Expense Claims

Expense claims should normally require:

  • business purpose
  • date
  • amount
  • receipt/evidence
  • cost centre
  • approver

Personal expenditure is not reimbursable merely because it occurred during programme travel.

46. Personnel Costs

Programme personnel expenditure should distinguish:

  • employees
  • contractors
  • consultants
  • advisers
  • volunteers

Each paid role should have:

  • contract
  • role
  • remuneration
  • time requirement where relevant
  • deliverables/accountability
  • approval
47. Founding Director Retainers

Where a founding director receives a programme retainer:

  • the programme role must be defined
  • deliverables must be identifiable
  • remuneration must relate to actual programme responsibility
  • invoices/payroll treatment must be appropriate
  • conflicts must be disclosed
Nobody is paid from Government programme funding simply because they hold equity, founder status or an advisory title.
48. Equity Is Not a Programme Cost

Share ownership, options, vesting or other equity arrangements are separate corporate matters.

They should not be charged to the Government programme as delivery expenditure.
49. Volunteer Costs

Volunteer support may legitimately include reasonable:

  • meals
  • travel
  • materials
  • safeguarding
  • training

Such expenditure should be recorded separately from employment compensation.

50. Contingency

The founding budget includes:

KSh 7,670,000

Programme contingency

The contingency is not an unallocated discretionary fund.

51. Contingency Approval

Use should require:

  • description of unexpected need
  • reason it was not reasonably budgeted
  • amount
  • programme impact
  • alternative considered
  • appropriate approval
  • updated forecast
52. Contingency Should Not Fund Scope Creep

Contingency should not routinely finance:

  • new programmes
  • unrelated events
  • unapproved hiring
  • discretionary branding
  • personal expenditure

Material scope change requires contractual and budget review.

53. Budget Variation

A budget variation may be required where programme evidence demonstrates that money should move between categories. The variation process should identify:

  • existing line
  • proposed line
  • amount
  • reason
  • effect on deliverables
  • approval required

Where the Government contract restricts variation, the contractual approval process applies.

54. Contract Variation

A change to budget is not necessarily the same as a change to contract scope. Material changes involving:

  • deliverables
  • price
  • duration
  • geographic scope
  • performance requirements

must follow the relevant contractual/legal variation mechanism.

55. Change Control Register

The programme will maintain a Change Control Register showing:

  • request
  • reason
  • financial effect
  • schedule effect
  • output effect
  • approval
  • status
56. Conflicts of Interest

Procurement decisions must be protected from personal financial interests. One Big Change will maintain a corresponding internal Conflicts Register.

58. Gifts and Hospitality

A Gifts and Hospitality Register should record material gifts offered or received. No gift should influence:

  • supplier selection
  • Government decision
  • school selection
  • payment
  • partner relationship
  • LocaeAwards outcome
59. Anti-Bribery and Anti-Corruption

The programme prohibits:

  • bribes
  • kickbacks
  • facilitation payments
  • payments for public influence
  • hidden commissions
  • procurement collusion
  • false invoices
  • fabricated expenses

Suspected misconduct must be escalated.

60. No Public-Sector Success Fees
No One Big Change employee, director, adviser or intermediary should receive commission calculated specifically on their ability to improperly influence or secure a Government procurement decision.

Commercial incentives for legitimate private-sector Traction Partner mobilisation may be structured separately and transparently where lawful and appropriate.

61. Whistleblowing

A protected reporting mechanism should allow concerns regarding:

  • fraud
  • bribery
  • supplier conduct
  • expense abuse
  • conflict
  • asset misuse
  • procurement manipulation

to be raised confidentially.

62. Fraud Response

Suspected fraud should trigger:

preserve evidence

↓

restrict further loss where possible

↓

notify appropriate senior authority

↓

investigate through an appropriately independent process

↓

obtain legal advice

↓

notify relevant authorities/contracting entity where required

↓

recover loss where possible

↓

document corrective action

63. Procurement Records

The programme will maintain clear procurement and expenditure files. One Big Change's own record-retention period will be aligned with:

  • the Government contract
  • applicable law
  • tax/accounting requirements
  • audit requirements

Where the Government contract requires longer retention, that requirement will apply.

64. Audit Trail

Every material transaction should be reconstructable from:

Need

↓

Approval

↓

Procurement

↓

Contract / PO

↓

Delivery

↓

Invoice

↓

Payment

↓

Accounting entry

↓

Programme outcome

65. Document Repository

Financial records should be held in a controlled system. Typical files include:

  • budgets
  • approvals
  • supplier quotations
  • contracts
  • purchase orders
  • invoices
  • delivery notes
  • bank evidence
  • expense claims
  • asset records
  • reports
  • reconciliations
  • audit documents
66. Monthly Bank Reconciliation

Programme banking should be reconciled regularly. Unreconciled items should be investigated.

The person performing the reconciliation should not be the sole person who authorised every underlying transaction.

67. Monthly Financial Close

The programme should operate a monthly close including:

  • bank reconciliation
  • supplier balances
  • commitments
  • payroll
  • expenses
  • accruals where appropriate
  • budget variance
  • cash flow
  • activation funds
  • contingency use
68. Monthly Government Financial Report

Subject to the final contract, reporting may show:

  • cumulative budget
  • current-period expenditure
  • cumulative expenditure
  • commitments
  • forecast
  • variance
  • milestone status
  • school activation expenditure
  • contingency use
  • Traction Partner value separately
69. Government and Traction Partner Money Must Not Be Blurred

Reports must distinguish:

Government Programme Funding

from

Traction Partner Cash

from

Traction Partner In-Kind Value

from

Other Grants

from

Commercial Revenue

This avoids overstating either Government expenditure or partner mobilisation.

70. No Double Counting

The same resource must not simultaneously be reported as:

  • Government expenditure
  • Traction Partner contribution
  • school contribution

unless the report clearly identifies the respective components.

71. In-Kind Resource Valuation

Partner in-kind value must be based on a documented valuation method. It should distinguish:

proposed

committed

delivered

verified

Only properly verified contribution should be presented as realised mobilisation.

72. Internal Audit / Assurance

The founding programme should include an independent financial review or internal assurance process proportionate to its size. Review may test:

  • procurement
  • supplier files
  • payroll
  • activation funds
  • travel
  • conflicts
  • assets
  • bank reconciliation
  • budget control
  • reporting
73. External Audit

The final Government contract should define any external audit requirements. The programme should nevertheless maintain its records at a standard capable of supporting external audit.

74. Government Audit Rights

Where required by the contract or applicable law, the relevant public authority and authorised assurance bodies may require access to appropriate programme financial records. The contract should define:

  • scope
  • notice
  • access
  • confidentiality
  • retention
  • cooperation
75. Corrective Action

Audit findings should result in:

  • responsible owner
  • corrective action
  • deadline
  • verification of closure

Recurring findings should trigger broader control review.

76. Value for Money Definition
Value for money is not simply: "Did we spend the entire budget?"

It asks whether resources were used to achieve the intended result appropriately. The programme will assess:

Economy

Were appropriate inputs obtained at reasonable cost?

Efficiency

Were inputs converted into outputs without unnecessary waste?

Effectiveness

Did the programme produce meaningful implementation change?

Equity

Did the model function across materially different school contexts?

Sustainability

Will the benefit continue after the expenditure?

Leverage

Did the programme mobilise additional useful resources?

77. Economy Measures

Potential measures include:

  • supplier price comparisons
  • travel cost
  • technology cost
  • venue cost
  • consultant rates
  • equipment market comparison

The objective is not automatically to choose the cheapest input. The objective is to avoid unreasonable cost.

78. Efficiency Measures

The founding phase should calculate:

  • cost per founding school
  • cost per completed baseline
  • cost per implementation cycle
  • cost per MicroSummit
  • field cost per county
  • support hours per school
  • evidence cost per school

These figures are especially important because they become the basis for Year 1 costing.

79. Effectiveness Measures

Value for money must also consider:

  • implementation priorities completed
  • practice change
  • leadership capability
  • evidence quality
  • resource utilisation
  • school continuation
Cheap activity that produces no useful implementation change is poor value.
80. School Activation Value

For each material school investment, the programme should ask:

What implementation barrier did this expenditure remove?

For example, it is not enough to state "KSh 800,000 spent on equipment." The programme should know:

  • why the equipment was required
  • whether it was used
  • what implementation changed
  • whether it can be maintained
81. Resource Leverage

The programme will calculate verified external mobilisation relative to relevant Government expenditure. However:

A high leverage ratio does not automatically mean high value.

Partner resources must also be relevant and usable.

82. Founding Programme Value-for-Money Questions

At the December Decision Gate, Government should be able to ask:

1What did the programme cost?
2What was delivered?
3What changed?
4Which expenditure categories created the greatest implementation value?
5Which costs were higher than expected?
6Which costs can reduce at scale?
7Which costs increase at scale?
8What could Hubs deliver more cheaply?
9What can become digital?
10What additional resources were mobilised?
11What cost should be expected per Core school in Year 1?
12Is national scale financially justified?
83. From Founding Cost to Year 1 Cost

The KSh 84.37 million founding programme should not be multiplied mechanically by 50.

The founding programme contains substantial one-off work including:

  • methodology development
  • legal setup
  • governance
  • platform development
  • national architecture
  • prototype processes

Year 1 also introduces new scale costs such as:

  • Hub operations
  • larger workforce
  • 500 Core schools
  • national technology
  • national evidence
  • 6,000-school network

Therefore Year 1 should be costed from actual resource requirements rather than simple multiplication.

84. Year 1 Indicative Budget

The current Year 1 planning model is:

CategoryIndicative Amount
National Programme Office & Executive DeliveryKSh 170M
50 LocaeHub Establishment & OperationsKSh 300M
500 Core School Implementation ActivationKSh 400M
Champion Training & Train-the-TrainerKSh 120M
6,000-School National Learning NetworkKSh 110M
National Field Travel & LogisticsKSh 105M
Evidence, Research & Independent EvaluationKSh 120M
Technology, Data & Digital InfrastructureKSh 100M
Expert & Specialist SupportKSh 85M
Traction Partner MobilisationKSh 45M
Legal, Safeguarding, Procurement, Audit & ComplianceKSh 45M
LocaeAwards & LocaeFestKSh 45M
Communications & National Knowledge ProductsKSh 30M
Programme ContingencyKSh 75M
TOTALKSh 1.75B

The figures remain indicative until the founding phase produces actual cost evidence.

85. Year 1 Cost Benchmarks to Be Produced

The founding programme must generate assumptions for:

  • cost per Core school
  • average Hub operating cost
  • facilitator cost
  • Champion development cost
  • travel intensity
  • Change Lens cost
  • evidence cost
  • technology cost
  • resource mobilisation cost

These become the financial model for Year 1.

86. Year 1 Milestone Release

An indicative Year 1 payment model is:

TrancheTrigger%Indicative Amount
1National programme inception20%KSh 350M
210 operational Hubs / 100 Core schools milestone20%KSh 350M
325 Hubs / 250 Core schools / mid-year evidence25%KSh 437.5M
450 Hubs / 500 Core schools / national infrastructure25%KSh 437.5M
5Year-end 6,000 network/evidence/completion requirements10%KSh 175M

These figures are planning assumptions rather than an approved payment schedule.

87. Hub Financial Control

LocaeHubs must not become uncontrolled mini-budget centres. Before any Hub controls programme resources, Year 1 must establish:

  • budget
  • authority
  • financial mechanism
  • procurement rules
  • reporting
  • evidence
  • audit access
  • asset control

Where appropriate, procurement may remain centrally or regionally managed rather than transferring cash to individual Hub Lead Schools.

88. Hub Cost Reporting

Each Hub should eventually report:

  • operating cost
  • implementation expenditure
  • number of Core schools
  • connected schools
  • resources mobilised
  • implementation outputs
  • evidence outcomes

This enables comparison of delivery models without creating a school ranking.

89. Cost per School Must Be Interpreted Correctly

Three different cost categories should be calculated separately:

Founding School Cost

Deep proof and methodology development.

Core Implementation School Cost

Structured Year 1 implementation.

Connected School Cost

Lighter network engagement.

Blending all three into one average will obscure the economics of the model.

90. Value for Money Decision Gate

The December Decision Gate should classify the model:

Green

Evidence suggests the programme can deliver meaningful value at credible national cost.

Amber

Potential value exists but costs/model need modification.

Red

Evidence does not support wider public investment at the proposed scale.

91. Year 1 Financial Gates

If Year 1 proceeds, financial controls should also operate through gates.

Gate 1

National mobilisation.

Gate 2

10-Hub replication.

Gate 3

25-Hub expansion.

Gate 4

50-Hub infrastructure.

Gate 5

Year-end completion.

Poor financial control at one stage should be capable of delaying the next expansion stage.

92. Procurement Readiness for Scale

Before moving from 10 schools to 500 Core schools, the programme must determine:

  • what should be purchased centrally
  • what should be purchased at cluster level
  • what should be Hub-coordinated
  • what should remain school responsibility
  • what should be sourced through Traction Partners
  • what procurement capability is required

This is a founding-phase output.

93. Preferred National Procurement Logic

The working principle should be:

Centralise where scale creates value

  • technology platforms
  • common licences
  • national evaluation
  • insurance
  • major framework services

Localise where context matters

  • certain field logistics
  • locally available services
  • context-specific support

Aggregate through Hubs where demand is shared

  • common expertise
  • training
  • selected equipment

The final structure will depend on evidence and applicable procurement requirements.

94. Procurement Should Not Drive the Education Need

The programme should avoid:

We bought it, therefore schools must use it.

Instead:

Change Lens

↓

Need

↓

Specification

↓

Procurement / Partner Response

↓

Use

↓

Evidence

Procurement is an implementation tool. It is not the implementation strategy.

95. Financial Performance Dashboard

The programme dashboard should show:

  • total contract value
  • cash received
  • expenditure
  • commitments
  • forecast
  • variance
  • contingency
  • school activation spend
  • travel
  • procurement status
  • partner cash
  • partner in-kind
  • milestone payment status
96. Transparency

Programme financial information should be transparent to the extent required by law, contract, Government reporting, audit and legitimate public accountability.

Transparency does not require publication of:

  • personal payroll details
  • commercially sensitive information
  • confidential supplier information

where such disclosure is not legally required or appropriate.

97. Procurement Record Retention

One Big Change will ensure its own programme-record retention supports the contracting entity's audit and contract-management obligations.

98. Beneficial Ownership and Supplier Transparency

Where applicable to One Big Change's participation in Government procurement, the required ownership information will be provided through the formal procurement process.

Material programme suppliers should also be subject to proportionate ownership/conflict checks.

99. Accountability

Kenya Managing Director / CEO

Overall programme financial accountability

Designated Kenya Finance Function

Day-to-day financial control

Chief of Staff & Operations

Programme operations

Finance, Resources & Investment Lead

Financial planning/resource architecture

Relevant Procurement / Commercial Function

Commercial procurement interface

One Big Change Board / Governance Structure

Governance oversight

Kenyan Legal & Governance Counsel

Legal compliance

The Government/public entity retains responsibility for its own public procurement, public-finance and contract-management obligations.

100. Pre-Contract Financial Readiness Gate

Before accepting Government programme funds, One Big Change should have:

Kenyan legal structure confirmed
Government contract reviewed
bank/accounting architecture established
finance lead identified
chart of accounts/cost centres established
procurement procedure approved
delegated authority approved
conflicts register established
supplier onboarding process established
expense procedure established
asset procedure established
fraud/whistleblowing process established
reporting templates established
audit/assurance route established
tax treatment confirmed
insurance requirements confirmed
101. Pre-Year 1 Financial Readiness Gate

Before moving to a possible KSh 1.75 billion national programme, Government should receive evidence that:

  • the KSh 84.37 million founding programme was financially controlled
  • audits/reviews were satisfactory or findings addressed
  • school activation expenditure was traceable
  • procurement files were complete
  • conflicts were managed
  • assets were recorded
  • financial reporting was reliable
  • unit costs are understood
  • the Hub financial architecture is ready
  • national procurement capacity exists
  • the Year 1 budget is based on actual evidence
102. Financial Success Test

The founding programme's financial architecture will be considered successful if Government can establish:

1where the money went
2why it was spent
3who authorised it
4what was purchased
5whether it was received
6whether the price was reasonable
7what implementation result it supported
8whether records are auditable
9whether conflicts were managed
10whether the cost model is credible enough to inform Year 1
103. Core Financial Promise
One Big Change Kenya will not measure financial success by the amount of money spent.

It will measure whether approved resources were converted into:

  • credible implementation
  • stronger school capability
  • useful evidence
  • sustainable change
  • additional resource mobilisation
  • a national model Government can judge on both outcomes and cost

Every shilling should be traceable.

Every material purchase should have a purpose.

Every payment should have authority.

Every national-scale cost should ultimately be justified by evidence from the founding programme.