Traction Partner & Resource Mobilisation Framework
How One Big Change Kenya identifies, mobilises, governs, matches, deploys and reports resources contributed by organisations outside the core Government commission - so the Change Lens identifies the barrier and the right partner helps remove it, rather than schools becoming supplier-led or donor-led. One Big Change Kenya, September-December 2026.
This Appendix sets out how One Big Change Kenya will identify, mobilise, govern, match, deploy and report resources contributed by organisations outside the core Government commission.
The Traction Partner model is intended to address a central implementation challenge:
Schools may know what needs to change but lack the money, equipment, expertise, infrastructure, technology or relationships required to make that change possible.
One Big Change therefore separates two functions.
Government Programme Commission
Funds the implementation infrastructure required to:
- diagnose
- coordinate
- support schools
- build capability
- gather evidence
- establish Hubs
- manage implementation
- report nationally
Traction Partner Resource Pool
Brings additional:
- finance
- equipment
- technology
- infrastructure
- expertise
- research
- professional development
- services
- connectivity
- other practical resources
The intention is not to substitute Government responsibility. It is to make better use of the wider resources available across Kenyan society.
The Change Lens identifies the barrier. The Traction Partner helps remove it.
Resources therefore follow evidenced need. They do not determine the need. This distinction protects the programme from becoming supplier-led, sponsor-led or donor-led.
Kenyan schools interact with many potential sources of support:
- Government
- businesses
- foundations
- development organisations
- NGOs
- universities
- technology companies
- employers
- professional associations
- community organisations
- philanthropists
However, support can become fragmented. A school may receive:
- devices without teacher capability
- software without connectivity
- equipment without maintenance
- training unrelated to its priority
- duplicated interventions
- short-term projects with no continuation plan
The One Big Change approach seeks to move from:
From
Available intervention looking for a school
To
Evidenced school need looking for the right response
A Traction Partner is an organisation that contributes resources, expertise or capability to help remove an evidenced implementation barrier. A Traction Partner may be:
- corporate
- foundation
- NGO
- social enterprise
- university
- employer
- professional body
- technology company
- infrastructure provider
- financial institution
- community organisation
- philanthropic organisation
- development organisation
Participation is based on relevance to identified need.
A Traction Partner is not automatically:
- a programme funder
- a programme supplier
- a Government contractor
- a sponsor with unrestricted access to schools
- an education-policy adviser
- an owner of programme evidence
- an organisation entitled to sell products to schools
- a decision-maker regarding school selection
Those roles must remain clearly separated.
Traction Partner contributions may include six broad categories.
1. Finance
- implementation grants
- programme sponsorship
- school activation support
- research funding
- event funding
2. Physical Resources
- equipment
- devices
- laboratory resources
- furniture
- learning materials
- assistive technology
3. Infrastructure
- connectivity
- energy
- classroom infrastructure
- technical facilities
- digital infrastructure
4. Knowledge and Expertise
- teacher development
- leadership support
- specialist expertise
- technical assistance
- mentoring
5. Technology
- software
- licences
- platforms
- technical support
- digital tools
6. Networks and Opportunities
- employer relationships
- pathways
- work exposure
- university links
- professional networks
- community connections
The Traction Partner mechanism follows a defined sequence.
School Change Lens
↓
Barrier identified
↓
Priority agreed
↓
Capability/resource gap identified
↓
Needs specification produced
↓
Potential partners identified
↓
Due diligence
↓
Partner matched
↓
Contribution agreed
↓
Resource deployed
↓
Use monitored
↓
Outcome evidenced
↓
Learning recorded
A contribution should not bypass this sequence simply because a partner wants to provide something quickly.
Each founding school will produce a structured resource-needs profile. The profile should include:
- school
- One Big Change priority
- identified barrier
- required response
- resource category
- quantity or scope
- estimated value
- urgency
- implementation owner
- sustainability implications
- evidence measure
The ten individual profiles will feed into one Founding Programme Needs Matrix.
| Need | Schools Affected | Type | Priority | Estimated Requirement | Potential Partner Type | Status |
|---|---|---|---|---|---|---|
| Example capability need | TBD | Expertise | TBD | TBD | Professional/University | TBD |
| Example equipment need | TBD | Physical | TBD | TBD | Corporate/Foundation | TBD |
| Example connectivity need | TBD | Infrastructure | TBD | TBD | Technology/Telecom | TBD |
The actual matrix will be populated from founding evidence. It will not be filled with assumed needs before the Change Lens is completed.
One of the potential advantages of the Hub model is the ability to aggregate similar school needs. For example, if one school requires a particular capability, the response may be expensive. If thirty schools require the same capability, it may be possible to create:
- shared training
- negotiated licences
- pooled equipment
- regional expertise
- Hub-based support
The founding programme will therefore examine where individual school needs can be converted into collective demand.
Every need should be classified as one of the following:
School Can Resolve Internally
No external resource required.
Programme Capability Required
One Big Change implementation support.
Government/System Support Required
Issue requires relevant public-sector response.
Expert Capability Required
Specialist knowledge.
Traction Partner Resource Required
Suitable external resource or contribution.
Mixed Response
More than one route required.
This prevents every implementation barrier from being automatically turned into a sponsorship request.
The programme will maintain a structured partner pipeline. Suggested stages:
Stage 1 - Identified
Potentially relevant organisation.
Stage 2 - Researched
Basic suitability established.
Stage 3 - Qualified
There is credible alignment with an evidenced need.
Stage 4 - Engaged
Initial conversation has taken place.
Stage 5 - Proposition Developed
Specific contribution proposed.
Stage 6 - Due Diligence
Required checks completed.
Stage 7 - Commitment
Written commitment agreed.
Stage 8 - Activated
Resource deployed.
Stage 9 - Evidenced
Contribution and outcome reported.
Stage 10 - Renewal / Expansion
Future relationship considered.
During the 90-day programme the initial operational targets are:
| Measure | Founding Target |
|---|---|
| School resource-needs profiles | 10 |
| National needs matrix | 1 |
| Potential Traction Partners identified | Minimum 20 |
| Qualified partner conversations | Minimum 10 |
| Needs mapped to potential partner categories | 100% of evidenced needs |
| Written commitments | Actual results reported |
| Cash/in-kind resources mobilised | Actual verified value reported |
The programme should not set an artificial cash target for the founding phase that encourages poor-fit partnerships.
A potential partner should be assessed according to:
- relevance
- capability
- reputation
- geographic reach
- financial/resource capacity
- safeguarding suitability
- sustainability
- alignment with identified need
- conflicts
- evidence expectations
- ability to scale
- willingness to work within programme governance
An internal partner assessment may use:
Strong Fit
Clear contribution to evidenced priority.
Potential Fit
Relevant capability but further discussion required.
Limited Fit
Some relevance but weak additional value.
Not Suitable
Contribution creates unacceptable risk or does not meet identified need.
This is an internal decision-support mechanism, not a public ranking of organisations.
Before material partner activation, appropriate due diligence should consider:
- legal status
- ownership
- reputation
- financial standing where relevant
- safeguarding
- data practices
- sanctions or significant legal concerns where applicable
- conflicts of interest
- relevant experience
- capability to deliver
- commercial intentions
- political exposure where relevant
- proposed school access
The depth of due diligence should be proportionate to the relationship.
A company may legitimately have a commercial interest in education. That does not automatically make it unsuitable. However, the programme must distinguish between:
Contribution
Resource provided to support the identified programme need.
Sale
A commercial procurement decision.
Traction Partner status does not grant preferential supplier status.
Where a Traction Partner also wishes to sell goods or services into the programme or Government-funded activity:
- the potential conflict must be disclosed
- procurement requirements must be followed
- Traction Partner status must not give an unfair advantage
- relevant decision-makers with conflicts should withdraw
- documentation should show how the decision was reached
Contribution must not become a back door into public procurement.
Traction Partners must not receive:
- preferential Government access
- influence over procurement
- influence over programme findings
- influence over Government policy
- guaranteed future contracts
in exchange for resources. No partner payment or contribution should be structured as consideration for influencing a public official.
Traction Partner status does not provide unrestricted access to:
- learners
- teachers
- school data
- parent contact information
- school communications
- classrooms
Access must be necessary for the agreed contribution and subject to school, safeguarding and programme controls.
Partner visibility should be proportionate to contribution and context. Possible recognition may include:
- programme reports
- partner acknowledgement
- LocaeFest
- agreed communications
- impact summaries
It should not result in schools becoming advertising environments.
Participation in One Big Change should not be used to:
- collect learner contact information
- target learners commercially
- create advertising audiences
- promote inappropriate products
- circumvent school procurement processes
This principle applies particularly where technology providers participate.
A material Traction Partner relationship should be documented. Agreements may cover:
- contribution
- value
- purpose
- beneficiaries
- delivery schedule
- responsibilities
- safeguarding
- data
- branding
- evidence
- procurement separation
- conflicts
- intellectual property where relevant
- termination
- reporting
Cash contributions should be recorded separately from:
- Government commission income
- school activation funds
- in-kind contributions
- commercial procurement
Restricted funding must be used for its agreed purpose.
In-kind resources may include:
- equipment
- staff time
- technology
- training
- facilities
- services
The programme will record:
- description
- quantity
- source
- beneficiary
- valuation methodology
- delivery date
- restrictions
- evidence
In-kind value should not be inflated for publicity. Valuation should use a reasonable basis such as:
- market price
- normal selling price
- documented service rate
- verified cost
- equivalent procurement cost
The valuation method should be recorded.
Partner reporting will distinguish:
Indicative
Potential or proposed value.
Committed
Written commitment exists.
Delivered
Resource has been provided.
Verified
Receipt/use has been confirmed.
Only delivered or verified contributions should be included in realised mobilisation figures.
The programme will calculate:
Verified additional resource value mobilised ÷ relevant Government programme expenditure
This is the resource-leverage ratio. It is one measure of value for money. It is not the only measure.
A programme that mobilises expensive but irrelevant equipment does not represent good value simply because the ratio is large.
Resource mobilisation should be judged on:
- relevance
- utilisation
- implementation impact
- sustainability
- additionality
Not simply total monetary value.
KSh 10 million of highly relevant capability may create more impact than KSh 100 million of poorly matched resources.
The programme should determine whether a contribution is genuinely additional. For example:
- Would the partner have provided it anyway?
- Is One Big Change redirecting existing activity?
- Is the programme creating a new contribution?
- Is it improving targeting?
- Is it increasing scale?
- Is it connecting previously fragmented work?
This distinction strengthens the credibility of partner-impact reporting.
Before accepting a resource, the programme should ask:
- Can the school maintain it?
- What happens when the free period ends?
- Is connectivity required?
- Are licences renewable?
- Who owns the asset?
- Who repairs it?
- Is staff training required?
- Does implementation depend permanently on the partner?
Resources that create unsustainable dependency may be rejected or redesigned.
Where equipment is provided, the agreement should clarify:
- legal owner
- custodian
- beneficiary
- asset-record requirement
- maintenance responsibility
- replacement
- disposal
Government-funded and partner-funded assets must remain distinguishable where required.
Technology partnerships require particular scrutiny. Questions should include:
- Is the tool actually required?
- Does it work in the school's connectivity environment?
- What data does it collect?
- Where is data hosted?
- Who owns the data?
- What happens when the licence ends?
- What training is required?
- Can the school afford continuation?
- Is there vendor lock-in?
Technology should solve an implementation problem rather than create a new one.
Universities may contribute:
- research
- evidence
- practitioner development
- evaluation
- specialist knowledge
- recognition
- student or academic expertise
Their role should be defined according to actual contribution.
A university logo is not a substitute for meaningful involvement.
One Big Change should seek to coordinate with existing programmes rather than duplicate them. Where an NGO or development organisation is already addressing an identified barrier, the programme may:
- connect the school
- align activity
- share learning where appropriate
- avoid unnecessary duplicate expenditure
One Big Change does not need to own every intervention.
Not all resources need to come from large national organisations. Future LocaeHubs may mobilise:
- local employers
- professional services
- local businesses
- alumni
- community institutions
- parents
- local expertise
This reinforces the principle of Harambee and local capability.
Local contribution must remain subject to safeguarding, transparency and conflict controls.
An expert may contribute:
- pro bono time
- subsidised time
- fully funded support
- commercially contracted support
The programme should record the basis clearly.
Experts should not be expected to work indefinitely without remuneration simply because the programme has social purpose.
For each identified need, the programme will ask:
What precisely is required?
↓
Is there an existing public provision?
↓
Can the school solve it?
↓
Can another founding school share capability?
↓
Is there an existing programme already addressing it?
↓
Is a Traction Partner required?
↓
Which partner is best suited?
This prevents unnecessary external dependency.
During the founding phase, One Big Change may convene targeted resource round tables. These should be organised around needs, not generic sponsorship. For example:
Digital and Connectivity Round Table
Teacher Capability Round Table
STEM and Technical Pathways Round Table
Inclusion and Assistive Technology Round Table
Wellbeing and Support Round Table
The founding Change Lens evidence determines which round tables are actually required.
A mature national model should seek a diversified portfolio. Dependence on one corporate or foundation creates risk. The portfolio should ideally include a mix of:
- Government
- private sector
- foundations
- universities
- development organisations
- local partners
- professional expertise
Subject to the December Decision Gate, Year 1 may establish a formal One Big Change Kenya Traction Partner Resource Pool. This would coordinate contributions around:
50 LocaeHubs
approximately 500 Core Implementation Schools
6,000 Connected Schools
The pool may contain:
- cash
- in-kind resources
- expertise
- services
- infrastructure commitments
It should not necessarily operate as one central bank account. Different contributions may be delivered through different controlled mechanisms.
The working strategic ambition is for the national programme to mobilise substantial additional resources alongside the core Government commission. An indicative planning range of approximately:
KSh 1 billion to KSh 3 billion in additional cash and in-kind resource value
may be tested during Year 1 planning.
This is not a guaranteed partner commitment and should not be presented as secured funding. The founding programme must determine whether this ambition is realistic.
The amount that can responsibly be mobilised depends on:
- evidenced school needs
- number and maturity of Hubs
- partner appetite
- Government alignment
- implementation capacity
- infrastructure requirements
- ability to absorb resources effectively
The final mobilisation target should therefore be established at the Decision Gate.
The Traction Partner model potentially enables Government to commission implementation infrastructure while leveraging wider society for additional implementation resources. Government is therefore not necessarily being asked to finance every:
- device
- laboratory
- licence
- specialist
- infrastructure requirement
through the One Big Change commission. The programme instead creates a disciplined mechanism for identifying what is needed and finding the most appropriate source.
External resource mobilisation does not transfer education-policy authority to private partners. Government remains responsible for its statutory mandate. Traction Partners participate within the programme architecture. They do not become parallel policymakers.
If the model scales, each LocaeHub may eventually maintain a local resource picture showing:
- common needs
- available expertise
- local businesses
- partner opportunities
- shared resources
- unmet requirements
This allows more needs to be resolved locally before they reach national level.
At scale, aggregated Change Lens information may allow One Big Change to identify patterns such as:
- repeated equipment gaps
- widespread capability needs
- regional connectivity barriers
- recurring inclusion needs
- professional-development demand
Appropriate aggregated information can then be used to design larger partner propositions.
Individual school or learner data should not be unnecessarily exposed.
The programme should maintain a dashboard covering:
Pipeline
- identified
- qualified
- engaged
- proposition
- committed
- activated
Contribution
- cash
- in-kind
- expertise
- technology
- infrastructure
Allocation
- school
- Hub
- national
Value
- indicative
- committed
- delivered
- verified
Evidence
- intended outcome
- actual use
- implementation result
Monthly partner reporting should include:
- new partners identified
- qualified conversations
- propositions issued
- commitments
- resources deployed
- verified resource value
- risks
- conflicts
- next actions
Government reporting should focus on programme-level value rather than disclose commercially sensitive partner negotiations unnecessarily.
Every significant contribution should eventually answer:
A photograph of equipment being handed over is not sufficient evidence of impact. Evidence should distinguish:
Delivered
↓
Used
↓
Useful
↓
Impactful
This distinction is central to the One Big Change model.
Partner renewal or expansion should consider:
- delivery quality
- evidence
- school feedback
- safeguarding
- value
- sustainability
- fit with future priorities
A large contribution does not guarantee continued partner status.
The programme should be able to end a relationship where:
- contribution is not delivered
- conduct creates safeguarding risk
- data is misused
- commercial pressure becomes inappropriate
- conflicts are unmanaged
- political activity compromises neutrality
- reputational risk becomes unacceptable
- partner influence threatens evidence integrity
Exit provisions should appear in significant partner agreements.
Traction Partners may support LocaeAwards, but sponsorship must not influence award outcomes. A sponsoring organisation should not:
- select winners for commercial reasons
- require its customer schools to win
- use awards as a sales incentive
- alter judging criteria
Recognition must remain evidence-based.
LocaeFest may provide an opportunity for partners to:
- share implementation learning
- demonstrate useful resources
- participate in practical conversations
- support schools
- hear research findings
It should not become a conventional trade exhibition in which access to decision-makers is effectively sold.
All public partner communications should distinguish:
Conversation
Initial engagement.
Collaboration
Defined activity.
Traction Partner
Agreed contribution.
Strategic Partner
Material, ongoing relationship.
Funder
Confirmed financial contribution.
These terms should not be used interchangeably.
Participation as a Traction Partner does not automatically transfer ownership of:
- One Big Change
- the Change Lens
- programme methodology
- national programme data
- programme branding
Partner intellectual property remains subject to its own agreement.
Partners may receive information necessary to respond to an identified need. They should not automatically receive:
- full school diagnostics
- confidential school data
- individual learner information
- unrestricted programme datasets
Information sharing should follow need-to-know principles.
Overall executive accountability
Kenya Managing Director / CEO
Commercial and Traction Partner strategy
Commercial & Strategic Partnerships Lead
Proposed founding lead: Kugan
Financial/resource architecture
Finance, Resources & Investment Lead
Proposed founding lead: Graham
School-needs validation
Education & Implementation Director
Institutional relationships
Strategic Partnerships & Institutional Relations - Kenya
Evidence
Evidence, Research & Learning Lead
Finance/control
Designated Finance Function
Legal agreements
Kenyan Legal & Governance Counsel
The Traction Partner mechanism will be considered promising if the founding programme can demonstrate that:
- school needs can be identified consistently
- needs can be converted into clear resource specifications
- appropriate partners can be found
- contributions can be governed transparently
- schools receive resources relevant to their priority
- those resources are actually used
- additional value can be measured
- partner involvement does not distort school priorities
- partner contributions do not undermine Government authority
- the model can plausibly operate through future LocaeHubs
At the December Decision Gate, Government and programme leadership should be able to answer:
One Big Change does not begin by asking what a partner wants to give. It begins by asking what a school needs to make implementation work.
The Change Lens identifies the barrier. The school and programme agree the priority. Government maintains the national direction. The right partner helps remove the barrier. And evidence determines whether the resource actually made a difference.